In November 2023, the UK High Court heard an action brought by Lendlease against AECOM arising from alleged fire-safety defects at the St James’s University Hospital Oncology Centre in Leeds. Lendlease had already been found liable to its client for almost £8 million in remedial costs for a range of defects affecting the hospital’s plant room, including inadequate fire compartmentation and other compliance shortfalls. Seeking to recover a portion of that loss — approximately £3 million — Lendlease sued Aecom, the engineering consultant responsible for elements of the design and fire-safety engineering. A judge dismissed the claim, largely due to limitation period issues — the defects occurred outside the window in which Aecom could be held liable under contract — but the case illustrates real-world legal liability claims against fire-safety consultancies and engineers. Background
The dispute centres on the plant room of the St James’s University Hospital Oncology Centre, a 13-storey healthcare facility built under a private finance initiative (PFI) and completed in 2007. In subsequent litigation, Lendlease was held responsible for £5,048,534.39 in damages for nine defects (plus over £2.9 million in a prior settlement) as part of wider remediation and defect costs.
Lendlease’s claim against Aecom — structured as a separate action to recover part of its own loss — focused on eight alleged design and fire-safety failures, including:
Lack of fire compartmentation in the plant room;
Omission of fire dampers where required;
Inadequate fire stopping zones; and
Issues affecting compliance with NHS fire-safety standards and building regulations.
Court DecisionThe High Court (Justice Stephen Eyre) dismissed Lendlease’s claim against Aecom on limitation grounds:
Aecom argued that any breach of duty must have occurred within 12 years of the cause of action — meaning the defect work was too old (completed well before the main contract date triggering liability).
Because the plant room work dated from 2006–2007, it fell outside the statutory limitation period for bringing the claim in 2019 when Lendlease issued proceedings.
The judge made clear that had the claim been brought within time, Aecom likely would have been found liable for some of the alleged defects; but the expiry of the statutory window precluded recovery on that basis.
Despite the dismissal, the case demonstrated how professional designers and fire-safety consultants can be the target of high-value liability claims by contractors seeking to pass on their own losses arising from fire-safety and building compliance failures. Why It MattersProfessional Liability ExposureThis case shows that:
Main contractors and developers may pursue fire-safety consultants and engineers for alleged design/inspection failings that result in substantial remedial costs.
Even unsuccessful claims can generate multi-million-pound damages exposures and legal risk for consultancies and engineers operating in high-risk sectors (health, residential, tall buildings).
Significance for Building Safety
It highlights that disputes about fire compartmentation, compliance with fire safety codes, and consultant duties are real and litigated — not just theoretical.
It also warns of limitations issues (time bars), reinforcing the value of robust data, clear records, and early risk assessment documentation for professionals in the fire-safety space.
NoteWhile this claim did not result in an award against the consultant, it nonetheless constitutes a real, quantified legal action over fire-safety defects — and it illustrates liability risk for fire-safety consultancies.
In November 2023, the UK High Court heard an action brought by Lendlease against AECOM arising from alleged fire-safety defects at the St James’s University Hospital Oncology Centre in Leeds. Lendlease had already been found liable to its client for almost £8 million in remedial costs for a range of defects affecting the hospital’s plant room, including inadequate fire compartmentation and other compliance shortfalls. Seeking to recover a portion of that loss — approximately £3 million — Lendlease sued Aecom, the engineering consultant responsible for elements of the design and fire-safety engineering. A judge dismissed the claim, largely due to limitation period issues — the defects occurred outside the window in which Aecom could be held liable under contract — but the case illustrates real-world legal liability claims against fire-safety consultancies and engineers.
Background
Court DecisionThe High Court (Justice Stephen Eyre) dismissed Lendlease’s claim against Aecom on limitation grounds:
Despite the dismissal, the case demonstrated how professional designers and fire-safety consultants can be the target of high-value liability claims by contractors seeking to pass on their own losses arising from fire-safety and building compliance failures.
Why It MattersProfessional Liability ExposureThis case shows that:
Significance for Building Safety
NoteWhile this claim did not result in an award against the consultant, it nonetheless constitutes a real, quantified legal action over fire-safety defects — and it illustrates liability risk for fire-safety consultancies.