BIMinAM Rethinking the O&M Process and Review 29-10-2026

BIMINAM RETHINKING THE O&M PROCESS AND REVIEW MEETING, 29-10-2026

Date: 29 October 2026 · 

Duration: 1 hour 26 minutes 26 seconds

  1. Meeting Objective

The meeting explored how the production and management of Operation and Maintenance (O&M) information can be improved. The main focus was moving away from treating O&M documentation as a separate handover activity and making it an integrated part of the design and construction process, ensuring information is accurate, verified, useful and maintained throughout a building's operational life.

  1. Challenges with Current O&M Handover

Participants highlighted several recurring problems:

  • O&M information is often delivered but rarely used effectively by facilities management and operational teams.
  • Documents and drawings are frequently outdated, fragmented or difficult to locate.
  • Information is often organised around construction work packages rather than the needs of building operators.
  • Clients may receive large volumes of information without understanding how to access or manage it.
  • Regulation 38, health and safety files, fire safety records and O&M documentation are not always properly coordinated.
  • Responsibility for updating information after handover is often unclear, particularly when facilities management contracts or service providers change.
  1. Client Requirements and Operational Needs

A key discussion point was that the process should start with understanding what the client and building operators actually need.

  • Clients should clearly define their information requirements, intended uses and expectations from the beginning of a project.
  • Facilities management teams should be involved early to identify the information required for maintenance, compliance and daily operations.
  • Employer's Requirements and project contracts should clearly specify what information must be provided, when it is required and how it should be checked.
  • Information should be structured around practical purposes rather than simply collecting documents to satisfy handover requirements.
  • Clients should retain control of their information and ensure it remains accessible when contractors or FM providers change.
  1. Progressive O&M Information and Verification

Darren Cutts highlighted the importance of starting O&M information collection from day one rather than waiting until practical completion. Paul Oakley presented an approach to progressive information management through technical submittals and product data.

  • Asset and product information should be captured as design and construction decisions develop.
  • Changes to specified products and approved alternatives should be recorded and tracked.
  • A project-level master list of asset types can help identify the required technical information and supporting documentation.
  • Information should follow clear checking, review, approval and acceptance processes.
  • Product information can be maintained in a central library and linked to BIM models and other project documents, reducing duplication.
  1. Digital Information, Ownership and Long-Term Management

The group discussed the practical and legal challenges of maintaining digital information after project completion.

  • BIM models and IFC files are not always suitable for direct operational use, and their accuracy and level of detail must be verified.
  • Design ownership, copyright, intellectual property and professional liability can affect who is permitted to modify original models and drawings.
  • Clients need clear arrangements for retaining, accessing and updating information throughout the building lifecycle.
  • A consistent information structure and clear responsibility for updates are essential to maintaining the Golden Thread.
  1. Next Steps
  • Develop a clearer framework identifying different client uses and purposes for building information.
  • Explore how clients can be better briefed on the information they need to manage their assets.
  • Continue developing progressive O&M information capture and technical submittal processes.
  • Consider how central product libraries and digital platforms can connect asset information across project stages.
  • Bring the discussion together into practical guidance that can support client requirements and improve the O&M process.

Key Takeaways

  1. Start with the client: Understand operational requirements before deciding what information to collect.
  2. Capture information progressively: O&M documentation should develop throughout the project, not be assembled at the last minute.
  3. Improve verification: Information must be checked and validated before it is accepted and handed over.
  4. Clarify ownership and responsibility: Clients need control of their information and a defined process for keeping it updated.
  5. Focus on usability: Successful handover means providing information that operational teams can easily find, understand and use.