To view the document scroll with mouse To leave a comment, scroll down with sidebar. If you wish, please put your email address in your comment, in case we want to follow-up.
Posted by George Stevenson from a linkedin exchange with Mark Austin Mark – George great work as always, maybe the challenge lies in ‘practical completion’ in JCT as opposed to ‘completion’ in NEC and FIDIC ICheme in infrastructure projects the handover and completion provisions can be very extensive including as-built information. This included on one project not receiving a Take Over certificate because of 2 missing as-built drawings
Anonymous
1 day ago
Posted by George Stevenson from a linkedin exchange with Joe Wharton – Creating bespoke waterproofing solutions across the commercial / industrial/ public /health and education sectors for both New Build & Refurbishment projects. E: Jwharton@garlanduk.com Joe – Charlotte Brogan (ACIOB) I have seen so many occasions of people not visiting site during works and providing quality assurance.
We go out twice a week and document the works and provide a report which is crucial in my opinion to transparency, quality, and accountability
Anonymous
1 day ago
Posted by George Stevenson from a linkedin exchange with Charlotte Brogan (ACIOB) Senior Design and Technical Manager at Fortem Charlotte – Brilliant piece of work, George Stevenson.
Having looked over the CLC / BIMinAM consultation details, focusing phase one entirely on what asset teams actually need is exactly the right starting point.
From a design management and document control perspective, the “how” requires a complete process shift. A true “as-built” relies on taking the contractor’s real-time site updates, paired with the site manager’s verified red-line drawings, to accurately update the master design information. Crucially, this validation must happen progressively—one work package at a time—rather than a mad rush at the end of the project.
To achieve the data integrity this guidance could benefit from the following statement; “Principal Contractors must contractually ensure designers are scoped to physically visit and audit the site during RIBA Stages 5 and 6.” If designers aren’t progressively on site verifying package completions alongside site managers, we cannot provide clients with the absolute clarity and trusted evidence that the Golden Thread demands. Looking forward to seeing how the next round of workshops tackles delivery!
Anonymous
1 day ago
Posted by George Stevenson from a linkedin exchange with Peter Cholakis
Peter – The problem isn’t a lack of technology. It’s what that technology has been asked to do.
Real progress in facilities management doesn’t start with a platform selection. It starts with process redesign: mapping how work actually flows, identifying where steps exist out of habit rather than necessity, and defining what “efficient” should look like for a given portfolio before technology gets layered on top.
Once that foundation exists, technology’s role becomes exactly what it should be — an enabler. It can consistently deploy the right processes, retain the knowledge that makes those processes work, and monitor performance against meaningful benchmarks rather than vanity metrics.
Anonymous
1 day ago
Posted by George Stevenson from a linkedin exchange with Ivan Young – Principal Designer (Building Regulations) | Author of the Gateway Bibles | Gateway 2 and Gateway 3, board-level strategy then the appointments underneath it | Competence assessed against the work Ivan – I am not sure this is as unresolved as the discussion suggests. As built information already has a definition.
The regulations require plans showing that the work as built complies, and require the information to be handed to the person who will hold it. On higher risk buildings that is settled, and nobody needs a workshop to discover what it means.
They also answer your question. Nobody certifies what they did not verify, because the person who made the change records the change, before it is made, with the affected documents revised.
Do that and the as built is a by-product rather than a deliverable anyone attests to at the end.
And I would note where the resistance is coming from. The firms worried about the implications for them and their insurers are not worried about the definition. They are worried about being asked to evidence what they built. George – Ivan Young – that is what people SHOULD be doing but it is clear that most are not doing so – and in the absence of those updated drawings and records, the client often gets a large number unverified drawings and schedules.
The industry clearly needs to change in light of regulations and potential enforcement but I feel we need to do it step by step and getting an industry-wide consensus of what “as-built” should include is one such step
Ivan – I disagree. Everybody understands what as built entails. If it isn’t provided to the regulator the application should be rejected. Understanding what as built means is not some higher level of understanding, it’s basic 1st year student content. Exploring new ways to counter the process serves nobody.
AS-BUILT INFORMATION, WHERE IT ACTUALLY SITS
SI 2023/909 reg 40(2)(c). The operative requirement. Such other plans as are necessary to show the work complied with all applicable requirements. A test, not a list. It never uses the words as built.
Reg 40(2)(d) to (f). Agreed documents, change control log, compliance declarations. reg 38(1) to (3). Handover to the relevant person by completion, filing structure retained, receipt acknowledged as sufficient.
38(5) defines it back to reg 40, so it carries no independent list.
Reg 31(2)(a) to (h). Properties of the information, not its content. Electronic, transferable, accurate, readable, available on request, secure, change logged, consistent.
Building Regulations 2010 reg 38. Fire safety information. Erection, extension and relevant change of use only. Not material alteration. Approved Document B vol 2 s19 and vol 1 s17. The only itemised list. Essential, plus additional for complex buildings. Guidance. BS 8644-1:2022 for structure.
We are once again attempting to change the new regime to suit old patterns and work methodology. we cannot cherry pick through the instruments to find the best fit, the documents should be read completely. George – Thanks for the detail Ivan.
If everyone knows what should be delivered, why do so few projects delivery complete as-built drawings?
Historically, architects were commissioned to do them informed by contractors redlining where things had changed.
That no longer happens but it seems that many projects dont do what you and I agree they should.
You are much more experienced in this than me so will have seen many more projects on the ground.
Are you saying that all the detailed MEP drawings have been 100% updated with the actual installation details?
Anonymous
1 day ago
Posted by George Stevenson from a linkedin exchange with Karen Bashiyants Director-Level Digital Construction Leader | Strategy, Methodology & Project Delivery | AEC
Karen – George, spot on. The gap is organizational before it is technical: as-built verification fails when nobody owns the evidence chain connecting design intent to construction reality.
Without clear responsibility for who creates the evidence, who verifies it, and who has authority to reject incomplete records, the process eventually pushes designers toward confirming conditions they cannot reasonably evidence.
How do you see the industry closing this accountability gap?
Anonymous
1 day ago
Posted by George Stevenson from a linkedin exchange with Marc Bradfield FCIOB – Director – Nucleus Compliance Group Ltd
Marc – your challenge point above “the suggestion that as-built information and handover information should be treated as entirely separate deliverables.”
I could not AGREE more.
Teams often become hyper focussed on ticking (often regulatory) boxes, with little understanding and fail to consider what is actually needed for a safe and successful building.
George – Thanks Marc. Your background and experience makes your contribution particularly valuable to us.
Anonymous
1 day ago
Posted by George Stevenson from a linkedin exchange with Charlotte Brogan (ACIOB) Senior Design and Technical Manager at Fortem
Charlotte – I am unable to make tomorrow’s meeting however my insights are as follows;
The answer lies in moving away from broad, retrospective sign-offs and shifting toward a targeted three-pronged compliance ecosystem:
1. Structured Primary Evidence: Works partners must capture live, geo-tagged, and time-stamped digital photographic evidence at the coalface during installation, backed by marked-up red-line drawings updated weekly & not left as a handover afterthought.
2. Risk-Proportional Design Audits: Instead of asking the design team to certify blindly, we enforce package-specific audit thresholds. For instance, the design team performs physical site audits on a minimum of 25% of Facades and 10% of Kitchen Installs. They aren’t signing off on everything; they are verifying a statistically robust sample size.
3. Strict RIBA Stage 4 Baselines: Any deviation from the signed-off RIBA Stage 4 design discovered during these audits must be formally logged, escalated, and redesigned or accepted by the principal designer before work proceeds.This shifts the burden from “unreasonable certification” to a verifiable trail of factual, sample-audited data.
Anonymous
1 day ago
Posted by George Stevenson from a linkedin exchange with Gavin Edwards – Experienced Architectural and Construction Specialist at GE Consulting
Gavin – Designers shouldn’t produce “As Built” information
George – Yet that is often what clients are given in their handover information
Gavin – it would just be the last construction issue by the consultant – you’d never go back to site and update your drawing to match what you found had been constructed – as built information is prepared by the contractor as his construction progresses
George – if only that really happened. I agree that it’s not the responsibility of the designer – but that is often what we get. As can be seen from the survey we did last week.
If you know of contractors who actually ensure all the drawings are truly “as-built” please ask them to contact me.
There must be a unicorn out there somewhere
Gavin – there’s meat here for a significant debate but if you call something As Built and your Services say thats what you’ll provide then the Client has every right to expect just that – I always delete As Built because I know it is not possible for a designer to provide that – I’m surprised that there’s not been more comments on the topic – a good subject though so 10/10 on your post…
George – Thanks Gavin. I think the important thing is for clients to understand the process of procuring buildings and services will need to change if they really need all of the drawings to reflect what was built.
I am not convinced that is necessary for ALL record drawings. We should prioritise what is really important and what is nice to have. Also have a status of Verified or Unverified.
Gavin – I agree totally but a cold beer needed
Anonymous
1 day ago
This comment is posted by george stevenson but originated from Duncan Howie an expert in Smart Buildings
Duncan – the data’s there; let’s use it –
Maybe not directly relevant, but, if nothing else, could designers be obliged to understand changes and incorporate learnings into future designs?
Anonymous
1 day ago
This comment is posted by george stevenson but originated from David Shepherd from Houses of Parliament project.
David – Thanks for this thoughtful post. The distinction between record information and verification of installed reality is important.
A designer’s final construction issue information may be entirely correct as a record of design intent and approved changes, without constituting evidence that the asset was installed exactly as shown.
What stands out for me is the reference to “the level of verification that has been applied”, but that naturally raises a further question: “when was that verification performed, and what evidence supports it?”
Many asset attributes can only be captured during a limited evidential window (e.g., installation and commissioning).
If identity, location, commissioning status or compliance evidence are not captured while directly observable, the industry often has little choice but to recover, infer or reconstruct the information later.
Surely, the next step is not just distinguishing between design information and installed reality, but also between information that is observed, derived and inferred.
The missing step is to define evidence capture during the evidential window as a contractual deliverable, not merely as handover documentation.
Anonymous
7 days ago
End of comments received directly by A Taylor…………..
Anonymous
7 days ago
As part of the draft consultation, I would offer the following observations:
Lack of a concise definition, or robust framework for definition, of the ‘physical’ meaning of as-built,
Blurring of the ‘as-built’ information, handover, and O&M information
Scope drift into validation, inspection and test plans, BIM, and asset management
Text that could easily mislead readers, either by its contents, or the context in which it has been placed
Significant repetition of content and language
The ancillary issues that the guidance touches on are important, but should not be included in this note as they are already extensively covered in other guidance.
Similarly, many elements of the draft could be split out into a separate ‘handover and O&M definition’ document – this would allow the as-built definition to be concisely and cleanly defined. Is there room for the working group to take time to take stock of the current comments and restructure the document?
Before we started the working group to define what “as-built” means, one of the contributors suggested we use the Oxford English Dictionary definition. “The adjective “as-built” describes something that shows the actual shape, size, condition, or structure of a building project or design just as it was finished, rather than how it was originally planned.”
Given that few clients are construction professional and might expect plain language to describe what they should expect, perhaps we should agree that is the required outcome and focus our discussion on the more complicated stage of HOW it can be done – or tell clients it isn’t possible.
Anonymous
7 days ago
—-Speaking as a building control professional, I feel it is critical that the document is circulated directly to the organisations who represent the profession, both as individuals and building control bodies. The guidance could be read as instructional for RBI’s and BCB’s, and Section 12 is quite detailed. Who has provided input to list the ‘what an RBI should reasonably be expected to check’ section for example? I understand the aims of the guidance, but I’m concerned that without direct consultation the effectiveness of the document will be reduced. There are also some clearer distinctions to be drawn out in respect of the term ‘as-built’. There are clearly differences between those elements required by legislation (and the differences for building types / work) and those elements required by contracts. Conflating the two will cause some confusion as they are very different things. In particular ‘as built plans’ will have two distinct meanings. For HRB’s there is a direct legislative requirement for this within the completion certificate application but this is not replicated for non-HRB’s. I’m happy to make my own comments as a building inspector, but I can’t speak on behalf of organisations obviously. I would recommend that before anything is progressed, input is sought directly from organisations such as LABC, ABCA, ARBI, CABE, RICS for example, on the issues relating directly to the building control function. Unless they are already involved, I doubt whether a response will be received by the 16th October.
Anonymous
7 days ago
Hi George,
I hope all is well. I have had a quick read and made some comments below. Some of which may be completely irrelevant.
Overall, the document represents a significant and positive step towards establishing a common industry understanding of what information should be delivered at handover and how that information should be verified, validated and managed throughout the lifecycle of a building. It addresses many of the historic shortcomings that have resulted in inaccurate, incomplete and unreliable building information being transferred between project teams, owners and operators. The emphasis on building information as an asset, together with the recognition that information must be planned from project inception rather than assembled at completion, aligns well with the principles underpinning the Building Safety Act, the Golden Thread and modern asset management expectations.
The document is particularly strong in establishing the need for accurate records of what has actually been built, rather than reliance upon design information and isolated change records. Its recognition that operational building users require information that remains understandable and usable over many decades is one of the strongest themes running throughout the draft. The distinction between As-Built Record Information, Building Information for Operation and Additional Client Asset Information provides a logical framework that is likely to improve consistency within future handover documentation. The requirements for verification, validation, evidence traceability, commissioning information and clear identification of safety-critical elements are all appropriate and consistent with post-Grenfell expectations. The emphasis placed on concealed elements such as fire stopping, structural connections and embedded services is particularly welcome given the difficulties repeatedly encountered in existing buildings where these elements are either undocumented or inadequately recorded.
From a building safety perspective, the document successfully captures many of the information management principles introduced through the Building Safety Act and associated regulations. It references Regulation 38 information, Golden Thread requirements for higher-risk buildings, dutyholder responsibilities, completion certification requirements, commissioning evidence, and the broader concept of information assurance. The guidance is therefore well aligned with the direction of travel of the Building Safety Regulator and the wider industry.
However, whilst the document is strong as a statement of principles, it is noticeably less developed as an operational standard. A recurring issue throughout the guidance is that it defines what good information looks like conceptually but does not define sufficiently what evidence is necessary to demonstrate compliance. The document frequently states that information should be verified, validated and trustworthy, yet it does not provide a consistent acceptance framework defining when information is considered acceptable or unacceptable. In practice, two competent reviewers could assess the same handover package and reach entirely different conclusions while both claiming compliance with the guidance. There is no clear threshold for missing information, incomplete records, conflicting evidence, or legacy information gaps.
The guidance also places substantial reliance upon clients defining information requirements at the outset of projects. Whilst this is sensible for sophisticated clients with established asset management teams, many clients, particularly smaller organisations, and housing providers with limited technical resource, may not possess the knowledge necessary to specify appropriate requirements. Although the document acknowledges this problem, it provides limited practical assistance. The inclusion of standard information schedules, example specifications or worked examples would significantly improve usability and reduce the likelihood of inconsistent implementation across the sector.
A further concern relates to legacy buildings and refurbishment projects. Much of the guidance appears to assume that comprehensive records either exist already or can be readily obtained. Many existing residential buildings, particularly older stock, contain substantial gaps in information regarding compartmentation, structural detailing, concealed services, cavity barriers and historic alterations. The document does not sufficiently address how uncertainty should be managed where information cannot reasonably be obtained without extensive intrusive investigations. Nor does it establish confidence levels for information based upon its source, age or reliability. I may have missed something but this appears a significant omission given that uncertainty management forms a substantial part of fire and structural risk management in existing buildings.
The guidance also appears to focus heavily upon the creation and transfer of information but is less developed regarding the management of that information throughout occupation. While references are made to ongoing updates and change control, there is little discussion regarding information degradation, data governance and the practical realities of ensuring that records remain accurate throughout the life of the building. From my experience, information often becomes unreliable not because it was inaccurate at handover but because subsequent alterations, maintenance activities and operational changes are not adequately recorded. More emphasis on information stewardship during occupation would strengthen the guidance considerably.
From a Building Safety Act perspective, the document should not be regarded as a complete representation of the regime. Whilst Golden Thread information and handover requirements are addressed extensively, there is very limited consideration of safety case development, resident engagement obligations, mandatory occurrence reporting, building assessment activities or wider occupied building duties applicable to Accountable Persons and Principal Accountable Persons. The guidance should therefore be viewed as an information management framework rather than a comprehensive building safety compliance document. Sorry if I have misunderstood this.
Of relevance from a fire safety standpoint is the limited treatment of BS 9991 and BS 9999 management assumptions. The document focuses strongly on physical assets, installed systems and compliance records but is considerably weaker regarding the management arrangements that underpin many fire strategies. Both BS 9991 and BS 9999 rely heavily upon assumptions regarding occupancy, management controls, maintenance arrangements, staff responsibilities, emergency procedures and ongoing operational management. Whilst the guidance requires fire safety information and operational information to be transferred, it does not explicitly require the handover of management assumptions, fire safety management plans or strategy assumptions registers. This is especially important within mixed-use developments where the interaction between residential, retail, office and ancillary occupancies form a fundamental part of the fire engineering solution. A future building operator may understand what was built but remain unaware of how the building was intended to be managed.
Similarly, whilst fire stopping records, fire door schedules, commissioning records and cause and effect documentation are appropriately addressed, the document places surprisingly little emphasis on the fire strategy itself. There is no strong requirement for an approved final fire strategy, records of departures from the strategy, validation of key assumptions or retention of supporting fire engineering assessments. Given that the fire strategy often represents the primary document explaining why safety measures exist, this omission is notable.
Overall, the document is a well-considered and valuable contribution to improving industry practice. It successfully addresses many longstanding deficiencies in handover information and represents a significant advance on traditional interpretations of as-built information and O&M manuals. However, it remains fundamentally a framework document rather than a definitive acceptance standard. To become a truly authoritative industry reference, further development is required around information acceptance criteria, evidence thresholds, management assumptions, safety case interfaces, treatment of legacy buildings and the practical application of BS 9991 and BS 9999 management requirements, particularly in mixed-use and higher-risk residential buildings. In its current form, I would regard it as an excellent statement of intent and a robust foundation for future industry standards, but not yet a complete or standalone benchmark for determining whether a building information package is adequate for long-term occupation, management and building safety assurance.
Sorry if I have misunderstood the criteria.
Regards,
Dave
Hi Dave – thanks for your detailedand well-considered contributions. I agree with everything you have suggested and these are the topics we will be discussing in Phase Two – the HOW – starting on the 20th October at 11am? the commenting is anonymous so If you can make that email me at george.stevenson@BIM-in-AM.com and we will send you an invite.
Anonymous
7 days ago
—George, here are my comments and recommendations.
In the introduction you talk about all the reasons why this is important, including efficiency. Efficiency can mean many different things, all of them positive. However, money gets everyone’s attention so I would add: resulting in improved profitability for the building owner and occupants throughout the building lifecycle.
You talk about handover at the end of any project. It might be more helpful to emphasize the goals of this initiative if you instead talk about the transition from the construction phase to the commissioning and operational staff. Make it look like a continuum with different organizations involved. Not an ending. In many other places you talk about the conclusion of a project. I’d recommend that whenever you can you use this same transition terminology instead of conclusion. This makes it sound more like a part of the building lifecycle, not the end of something.
You get to the bottom of page 4 before you state:
• Both new build and work on existing buildings.
This is important enough that I would recommend stating this up front as a part of your introductory statements, even if it becomes a duplication. There are contractors who specialize in retrofits and upgrades. They could easily assume that this does not apply to them when you read the previous pages. It all sounds like the focus is new construction.
I would recommend that in section 5 as a part of verification and validation process that you call out the Commissioning step and require that the commissioning agent confirms that all live systems (BAS, lighting, security, fire, etc.) agree with and accurately reflect the as-built drawings before releasing the contractor from their obligations. This not only confirms accurate and reliable data on day one but sets the stage for keeping them in sync as the building continues its lifecycle.
In your BIO section I recommend that you include conformance to all industry or government standards for systems providing live data. Obviously, I am thinking of BACnet for live building automation data but there are standards for most subsystems. When ownership of a building changes part of the required deliverables should be identifying any cases where this is not true. In my example this would allow the new owner to introduce analytics or FDD value-added applications to improve building operational efficiencies. You want to avoid the surprise of needing to do a rip-and-replace of building systems without prior knowledge of that being necessary.
I am not sure where this belongs but somewhere it should be stated that all building data is the property of the building owner. It is not allowable for a contractor, or one of their suppliers or subcontractors, to lock the building owner out of access to the as built or real time data for the building.
The contractor should not be allowed to just walk away from a project. There should be a substantial warranty period for which they are required to provide any information that was legally required and they omitted from project deliverables.
Anonymous
7 days ago
—–As a Safety Officer, I believe that health and safety information should be an essential part of the handover documentation. It should include:
– As-built drawings showing safety-critical systems and installations.
– Fire protection and emergency arrangements.
– Risk assessments and safe operating procedures.
– Inspection, testing, and maintenance records.
– Relevant safety information for future maintenance and operations.
Providing accurate and complete safety information at handover will help building owners and operators manage risks effectively throughout the building’s lifecycle.
Yes – I fully agree but we expect to cover that in the HOW workshops. which start on the 20th October at 11am? the commenting is anonymous so If you can make that email me at george.stevenson@BIM-in-AM.com and we will send you an invite.
Anonymous
7 days ago
——-Kevin added a whole document that needs review too …Overall, I believe this is a very valuable piece of industry guidance. The five guiding principles, in particular, and the “trust vs. usability” framing in Section 7 are both insightful and highly relevant.
While reviewing the document, I noticed a few points that I felt would benefit from further consideration, along with some minor areas where additional polishing may be helpful. I thought it would be useful to bring these to your attention before the document is finalised.
Please find attached a PDF highlighting the points for your review and consideration.
Apologies but I don’t think we have received your PDF document. Can you email it to me at george.stevenson@BIM-in-AM.com and we will also send you an invite to the HOW workshop on the 20th October.
Inspection and Test Plans, An ITR often has no context without the corresponding inspection and test plan which sets out the tolerances to be met!
Without the above the building operator maintainer can not start understand what has changed from the design intent and the work arounds required to keep the occupants safe.
Note that the approach by CLC and the above comments relates to BR requirements and not CDM2015 requirements.
The CDM 2015 requirement is suggested to be for an As-Built ‘access and working space drawing’ showing vehicle and pedestrian routes around the site and structures, access to below ground services, access to services inside and outside the structure, locations for access equipment, cranes and emergency response vehicles. The drawings need to show all installed plant, equipment fittings and fixtures and the access space around them and warnings where work equipment is required to access / reach a working space. These drawings are also suggested to identify locations where services are isolated.
Anonymous
7 days ago
—–MD of smoke control subcontractor SE Controls, was particularly positive and said the timing was perfect because he is leading a standards group for smoke control and he said what they are releasing seems to align well.
It’s a big document to consume, so I asked ChatGPT to produce a summary.
It looks quite good to me and I plan to issue this to my contacts.
Is it OK from your perspective?
Anonymous
7 days ago
My initial feel is that the product safety aspect is very light touch and needs reinforced, and equally I have asked if our (SAFed) committee can consider preparing something (if we don’t have a document already) for lifts similar to the fire door documents produced by NAHFO.
Anonymous
7 days ago
However , could I suggest that there ought to be a max. one page Appendix in the proposed revisions to the L153 Guidance on CDM , as an addition to the Appendix 4 Health & Safety File explaining what “As-Built Information” is required. This issue must be proportionate for the users.
Inspection and Test Plans, An ITR often has no context without the corresponding inspection and test plan which sets out the tolerances to be met!
Without the above the building operator maintainer can not start understand what has changed from the design intent and the work arounds required to keep the occupants safe. Note that the approach by CLC and the above comments relates to BR requirements and not CDM2015 requirements.
The CDM 2015 requirement is suggested to be for an As-Built ‘access and working space drawing’ showing vehicle and pedestrian routes around the site and structures, access to below ground services, access to services inside and outside the structure, locations for access equipment, cranes and emergency response vehicles. The drawings need to show all installed plant, equipment fittings and fixtures and the access space around them and warnings where work equipment is required to access / reach a working space. These drawings are also suggested to identify locations where services are isolated.
Anonymous
7 days ago
The next tranche of comments have been received directly by Anthony Taylor and are transcribed/copied across to this record for the purposes of ‘The Record’ being in one place and to facilitate analysis.
Anonymous
8 days ago
We fully support the requirement to provide accurate handover information, however the guidance as currently written is overly prescriptive and too open ended. The guidance purports to outline the minimum level of information, however, also suggests that clients should be able to request any additional information they require. The document is likely to be included in future contract requirements and therefore needs to be very clear about what is the minimum and optional extras, which will invariably have a cost implication. If not clarified this could delay handovers and impose a significant additional burden on the project delivery teams. In discussion with our consultants it is clear the level of verification of information will not be possible nor is it their understanding or indeed the intention of any regulations.
See below comments to individual sections.
Section 1: Purpose of this guidance
1.1 As noted above there reference to minimum content is not correct noting references elsewhere in the document (See 9.1), which intimates the provision of whatever information the client requests if not defined at contract stage.
Section 2: Scope and intent of this guidnace
1.2 The guidance notes the aim to clarify the meaning of ‘As-Built’ information to provide a reference for both Building Control bodies, Third Party Reviewers, Contractors, Clients, etc.
Its is worth noting the requirements under the Golden Thread will differ from the requirements under for the other interest groups. The guidance needs to set this out clearly to avoid confusion at project level.
Section 3: Contractual and legal considerations
1.3 No comment
Section 4: Acknowledgements
1.4 The absence of the major residential developers on the list of collaborators is unfortunate.
Section 5: Key principles
1.5 No comment
Section 6: What information we are referring to
1.6 We disagree with the statement that ‘final design for construction’ documents are ‘NOT PRACTICABLY USABLE’ by building owners and not acceptable under the proposed guidance.
It is our experience that drawings first need to be updated prior to construction works and should therefore reflect what has been constructed. The Principle Designer will review the information prior to handover and provide a statement that this represents an accurate record of the building as-constructed.
Section 7: The key attributes for as-built information
1.7 It is noted that the level of information may exceed the level required to obtain regulatory approval with example given of performance specifications. Again this is not our experience as a performance specification will stipulate the detail design requirements to be provided by third parties prior to regulatory approval and handover.
1.8 The guidance proposes intrusive access ‘where appropriate’ to check life safety systems as part of the handover process. This seems an extreme requirement noting inspections and first of kind installations can be reviewed and recorded throughout the project duration.
1.9 There is also a requirement for an ‘independent witness’ for life safety systems. There needs to be a definition of independent as this has the potential to create an excessive burden on the project.
Section 8: definition of specification
1.10 The guidance requires a record of information which is unverified or unverifiable. More detail is required to understand the potential scope for the this requirement.
Section 9: Minimum levels
1.11 The guidance requires information to be conveyed in a format that a lay person could easily understand. The level of detail stipulated elsewhere in the requirements will make this difficult. Rebar detailing and structural calculations are unlikely to be easily interpreted by lay people.
1.12 Levels of detail should be agreed prior starting the project. This is not always possible as buildings may only be sold to a new owner midway through construction.
1.13 The requirement to record any work not complaint with regulation at handover stage does not make sense. Surely buildings would not be handed over until regulatory compliance is achieved?
1.14 The statement that the default position would be that he client is entitled to provide any further information if not agreed otherwise is unfair. Again should this guidance not be looking to set a minimum? Any additional information can always be requested at contract stage as this will cost implications.
1.15 ‘For concealed or embedded elements (structure, services, fire stopping), the record must be sufficient to locate and properly identify the product/item without destructive investigation.’ This is not possible for elements like steel re-enforcement.
1.16 Design calculations to prove regulatory compliance as a stated requirement is not currently provided and will involve a vast amount of additional information, which will presumably also need to go through the verification process at handover.
1.17 ‘Independent verification’ need to be more clearly defined as open to interpretation.
1.18 Safety critical elements is noted as needing inspection and verification by the professional responsible for designing the element. This will require cost additional inspection regimes from the appointed consultants for something competent project managers should be able to complete.
1.19 Reference to other guidance documents are noted in 9.6. This appears to move beyond the intent of defining minimum requirements.
Section 10: Guidance specifically for clients and building owners
1.20 The guidance recommends that end users can demand information in excess of pure statutory requirement. Again this appears to go beyond a minimum requirement as per the stated intent in the introduction.
Section 11: Illustration of information requirements collation across building lifecycle
1.21 No comment
Section 12: Statutory requirements for information and the requirements
1.22 No comment
Section 13: Statutory requirements for building information
1.23 No comment
Anonymous
11 days ago
I am an ARB-registered architect who has switched to producing information-management software for the AEC sector, so I should declare a commercial position. My comment is made in my professional capacity, with the safety of the public in mind. Two kinds of information in the handover pack
The draft rightly anchors trustworthy information in people: how it was collated, verified and validated, and by whom (section 7), and competent, independent sign-off (9.5). The provenance, traceability and signatures it asks for are valuable because a competent person stands behind them. My reason for writing is not to challenge that, nor to debate the meaning of the term “as-built”, but to point out that the pack holds two distinct kinds of information, and that emerging AI workflows threaten the competence behind one of them in a way the record itself cannot surface.
The first kind is a record of the building: drawings and models of the final state, the location of concealed items, attribute data. For these, as an oversimplification, “verification confirms the information matches what was built” works as a test, and automation is little threat where human sign-off is required, because the act of verifying is a distinct act grounded in the physical world.
The second kind is derived from documents, not from the building: key design assumptions for future modification, derogations accepted by the client, residual risk registers, outstanding issues and assumptions. For these there is no building to check against, and the requirements can say a register must exist but cannot say what must be in it; what belongs in it can only be found by reading the project record. The draft asks for traceability (9.2) and for registers to name their sources (9.6), but it does not ask anyone to read a compiled register back against the record it was drawn from, so nothing in the project’s own verification confirms that such a register is complete. Where AI compilation will land, and what it does to the reviewer
This is important because it is the content people will want to use AI to compile, because it is the thousands-of-documents part of the pack, and as a result it is where the behavioural problems will be the hardest to guard against. The people compiling it are designers, contractors and information managers whose job is producing and passing on this information, for whom checking feels like overhead, even if necessary and critical overhead.
The AI promise of compiling with a tool and “fixing the remaining few per cent” is the path of least resistance and would be seen as welcome by many. In this context, fixing the remainder means reviewing the tool’s output rather than reading the sources, and vigilance in reviewing output is well documented to fall as the tool appears more capable, and, critically, to fall without the reviewer being aware of it. Once a certain accuracy threshold is reached, reviewer confidence increases, automation complacency increases, and review skills can atrophy as a result.
Worse, the omissions are the hardest to spot, because items the tool left out give the reviewer nothing to look at, and over time the problem compounds. The ability to notice that a register is incomplete comes from having worked through material of that kind, and if the compiling is delegated, that familiarity stops being built. The record would still carry its signature, provenance and traceability, but the competence that gives those attributes their value would have thinned, and nothing in the record would show it. Professionals aware of this phenomenon are less likely to fall for these failures, but current industry discourse is far too quiet on this and it remains a growing risk area. Deterministic and probabilistic compilation
Whether this matters depends on how the compilation is done. A deterministic process can be tested, its errors corrected through its logic and its output reconciled against a known rule. A probabilistic one, as most current AI systems are, makes a fresh judgement on every item, so confirming that each item was compiled correctly becomes the human’s task, which is the monitoring task described above. AI run alongside an existing review reduces risk; AI run in place of the first read, with a human fixing the difference, is the direction of travel much of the industry discussion assumes and can, counterintuitively, substantially increase the human scope of a review task and make proportionate review a much muddier concept. Three suggestions
9.5 should say what verification means for content whose completeness can only be established from the project record, since matching the building does not apply. A competent, independent person should check the compiled register against the documents it was drawn from and record the evidence chain, starting from the documents and confirming that each relevant item reached the register. Checking the other way, from the register back to the documents, only shows that what is there is right; it does not show that nothing is missing.
Where a tool did the compiling, the record should say so under section 7’s first question, and say whether the tool makes a judgement on each item or applies a repeatable rule. If it makes a judgement, the compiled content should carry the draft’s existing “unverified” marking (8.3, 9.6) until someone has done the check above in full detail and reconciled that autonomous judgement with their own.
Phase two should consider which compilation methods are acceptable, and how the people signing off keep the competence to notice what a tool has left out, or tackle convincing-looking errors.
The likely objection
The likely objection is that the source documents were already signed off by the designer or contractor. That sign-off vouches for the documents. It does not vouch for whether the register reflects them as a competent person reading the originals would have understood them. Nor are the designer and contractor immune: they may meet the same automation complacency when producing those documents, so errors missed at their sign-off pass through to every later stage. This is a conceptual problem for the lifecycle of information on a project, not only for its finalisation at handover, which is why addressing it is vital. Prompt and document injection, where text inside a source document steers or corrupts the tool’s output, is a separate and more complex facet of the same problem and not addressed here. Further research
The phenomenon of AI omissions for professional reviewers is set out in a preprint, The Omission Gap (SSRN, 2026), and I am continuing research at the intersection of professional competence, document integrity and AI systems. I would be more than happy to discuss this further if it would be beneficial to the consultation.
You can message info@vbrief.ai to reach me.
James Wright-Zhang
Anonymous
12 days ago
Adding to the below post, see below further thoughts
Include calcs where they are needed to safely carry out future work: examples
Safe working loads for roofs, platforms or structures.
Geotechnical design assumptions relevant to future excavations.
Information explaining residual hazards that cannot be understood from drawings alone.
Summary of key engineering calculations demonstrating operational limitations
Do not include calculations when they have no relevance to H&S; examples
Full Eurocode calculation packs.
Draft design iterations.
Finite element models.
Routine design checks.
Internal design assurance records.
Design review comments.
Commercially sensitive calculation files that add no future safety value.
Calculations supporting elements that were not built
A future designer does not usually need to see every page of bending moment, fatigue or reinforcement calculations. What they need is:
design assumptions;
design limitations;
residual risks;
safe loading information;
any constraints on future modification.
Ask “Would a competent engineer, maintainer or contractor need this information to safely alter, maintain or demolish the asset in the future?”
Anonymous
12 days ago
There needs to be a consideration of the production of appropriate design and design check calculations, to be provided as part of the as-constructed information. Below are some pointers.
NR standards include provision of suitable as-built drawings and design and check calculations to allow future use.
A common-sense approach is needed, with some suppliers offering meaningful packs which include key outputs of calculations where they are critical to safe future use, maintenance, alteration, or demolition,
Information on design loadings,
Key calculations demonstrating structural strength and stability,
Utilisation factors,
Ground investigation information,
Construction sequence,
Fire engineering design
Departures from standard design requirements
Some suppliers produce reams of wholly inadequate outputs which are meaningless to anyone looking at them in future, hence are useless.
A test is “ Will someone need this calculation (or its outcome) to avoid risk in the future”. Guidance on what a calculation pack within a H&S file should contain is welcomed, but here is a quick summary suggestion.
“The CDM Health & Safety File should not replicate design calculations but must clearly identify and communicate all safety-critical design assumptions, limits, and constraints derived from those calculations that are necessary to ensure the safe operation, maintenance, alteration, or demolition of the asset”
Network rail have clear expectations for H&S files (including as constructed drawings) in standards NR/L2/OHS/0047, and NR/L2/INF/02202. Suggest a paragraph is added referencing other such documentation or acknowledging such standards exist e.g. add thus “This document compliments other documents. For instance, Network rail have clear expectations for H&S files (including as-constructed drawings) in standards NR/L2/OHS/0047, and NR/L2/INF/02202″
Anonymous
12 days ago
On page 4 please add a forth bullet after “It applies to” to read thus:-
Where the CDM regulations provisions for H&S files apply
Anonymous
18 days ago
Our principal argument set out in the file note we produced for delineating and defining scope of For Record Drawings is that consultant Record Information and physical verification of the completed works are different and discrete evidential functions, and should remain so. The note defines consultant information as the final coordinated design intent, updated for formally notified and approved changes, while expressly excluding continuous supervision, comprehensive dimensional verification and certification of every installed element.
What the guidance seeks to establish is a somehow all-encompassing unified record where distinction between functions seems blurred and therefore either renders responsibilities null or infers total responsibility for all aspects on a specified agent (client / PC / PD / other dutyholders), depending on how you view it, which flies in the face of the regulations key tenets of sequential responsibilities discharged by competent actors towards a holistic record – Golden Thread.
What it seems to legitimately be trying to achieve is trustworthy, usable lifecycle information.
Its difficulty is that Sections 6–9 and Appendix 1 repeatedly moves between:
an overarching composite handover record;
individual drawings, models and data;
verification of documentary requirements; and
verification of the physical works.
Terms such as “authoritative record”, “verified and validated record information of what has actually been built”, “As-Built Drawing”, and “As Constructed Record Document” therefore risk attaching the assurance status of the whole package to each consultant-produced record drawing. Recommended consultation position:
Retain a composite, evidence-led objective, but expressly define consultant’s For Record Drawings / Record Information as one constituent source, explicitly stating that an individual designer’s record information is not certification of the physical installed condition unless a separately scoped, competent verification service has been commissioned and performed. This may result in the light of responsibility for this information falls on the PC or client, but we don’t feel that it should as it is not necessary or supported by the regulatory framework. What is the legislative position:
Regulation 31 requires approved and revised documents, change records and compliance evidence to be maintained through the Golden Thread.
Regulation 38 transfers the completion application, accompanying documents and relevant operational information to the relevant person.
Regulation 40 requires the latest agreed documents, plans necessary to show compliance, the completed change-control log and PD/PC duty-fulfilment declarations.
The BSA-2022 enables regulations covering certificates, information creation and retention, and inspection/testing – which taken together suggests ‘an authoritative record’, however it does not itself appoint the architect (as PD, or another design dutyholder) as universal verifier of the completed asset, which clearly is beyond their independent design scope or expertise.
There is nothing in the legislation that determines that any one dutyholder has an obligation to prove that contractors installed every element in accordance with their design.
Equally, as Pricipal Designer, the GW3 declaration is not to be worded as an architect’s certification of dimensional probity, workmanship, concealed construction or correctness and appropriateness of all installed products.
Likewise, the Principal Contractor is not require to re-survey every trade installation; the legislation determines that the PC is responsible for supporting a managed evidence chain using competent contractors, specialists, inspections and tests, in conjunction with technical and testing standards and approvals for the materials and product specified and/or controlled through the orchestrated change protocols (and records).
The BSR’s fundemental remit is to inspect the completed work and issue the completion certificate only if, after taking all reasonable steps, it is satisfied that the work complies, prescribed information is complete and accurate, and required information has been handed over. This does not constitute a requirement to insist on reconstituting all contributors inputs, across the entire and lengthy process (Stage 4-6, over sometimes.many years), into an authoritative ‘As-built’ production. Their final assessment is not replaced by a designer’s record drawing; even their Completion Certificate is evidence, but not conclusive evidence, of compliance.
The fundementals underpinned in regulation…..
There is no provision requiring the architect to certify that its drawings physically match every installed condition.
This conclusion is interpretive, but follows directly from the allocation in the regulations:
Designers are responsible for compliant design and sufficient design information;
the PD manages design compliance;
the PC manages and evidences construction compliance;
the client owns the completion application and information arrangements;
and BSR makes the regulatory determination after inspection post-completion.
Composite traceability is the essence of the golden thread evidence rather than Composing reality….
This in essence gathers together the approved design, authorised changes, construction records, installed systems, tests, non-conformances and the accepted baseline. This is substantially the evidential suite proposed in our previous file note outlining ‘For Record’ suites of information from relevant dutyholders.
A reasonable analogy (perhaps not a brilliant one) would be that of an auditor (BSR) looking at a company’s financial report at the end of the year (post-completion) – they aren’t required to observe each and every receipt for each and every purchase, they are required to evaluate and enquire in order to satisfy themselves, taking all reasonable steps, that the book represents the actuality. The responsibility rests with the company (Dutyholders) that their report is accurate. But its the process across the year that’s important (The Golden Thread) not some retrospectively produced overarching composite record that attempts to bind every element.
I agree with the central concern expressed by ATGL and other designers.
A designer’s final construction or record information should not be interpreted as certification that everything shown was physically installed exactly as drawn where the designer has neither been commissioned nor able to verify that fact.
That distinction is important.
However, I do not believe the answer is therefore to redefine “as-built” so that information describing design intent can be accepted by clients as a record of physical reality. Instead, we need to distinguish clearly between what information represents, who is responsible for producing it, and the level of verification that has been applied to it. What does “as-built” mean?
One of the most useful outcomes from three months of discussion involving more than 100 contributors is that a seemingly simple term has exposed a much bigger industry issue.
The comments that the guidance of how the term “as-built” should be interpreted by clients and those people occupying buildings should be much (much) shorter are well made.
Here is my suggestion – from the Oxford English Dictionary “The adjective as-built describes something that shows the actual shape, size, condition, or structure of a building project or design just as it was finished, rather than how it was originally planned.”
On that basis, a final construction issue drawing can be extremely valuable record information, but if nobody has established whether the completed construction corresponds with it, it should not be presented to the client as verified evidence of the installed condition.
That does not make the drawing wrong, nor does it make the designer responsible for verifying construction. It simply means we need to describe its evidential status accurately.
Indeed, this appears to me to be broadly consistent with ATGL’s own position: consultant record information and physical verification are different evidential functions and should remain distinguishable.
The question therefore becomes: If the designer is not responsible for verifying the installed condition — quite reasonably in many cases — how does the industry collectively provide the client with a trustworthy record of what has actually been built?
That is the gap I believe the guidance needs to address. The client should not have to reconstruct the building at handover
Anonymous
18 days ago
Our general consensus, and from correspondence from the ATLG is that this document is just too long – who is the intended document for?
The document really needs to be restructured into a concise actionable checklist with signposting guidance. Certainly, a case of ‘less is more’. Does this document really need to repeat core definitions, client duties etc – should it not sign post back to already agreed and issued CLC documentation? Slight irony that the document itself states the need for ‘value over volume’ and then sets this all out in a 45 page document!
There is a lack of practical realism if it thinks this document will really apply to all building work – from small domestic projects to large complex ones. Have they ever seen how a small domestic project works – getting one drawing let alone a full as-built set would be considered a win. If you make something too academic or too paperwork heavy, then the smaller / lower end will just ignore it. Would recommend there is a ‘lite’ version of this document for domestic / smaller end and the more detailed version for the larger more complex projects. There should certainly be a split between HRB and non HRB is this document – a clear split.
It doesn’t really align with our viewpoint – we still see the need for As-Built to actual be Record Information (by consultants) and Verification / Declarations (by contractors).
Where it states – ‘Those using an as-built record must be able to trust the information on or in the record’ , whilst an understandable ask -the ‘as-built record information’ is only at a moment in time. If say 10 years have passed, anything could have happened since then – therefore blindly trusting aa-built record information should not be encouraged, the information must be verified and checked prior to any works taking place even if the information is trusted.
Notes on digital information needs caveating – the building will last likely longer than any current supported platform or format, how is its access maintained…..it’s only 30 years really since floppy disks / CD-ROM’s etc or VHS – and you’d struggle to access that now.
The document is text heavy – maybe some diagrams of tables / matrix would be clearer? The practicality of this document with regards the day to day needs to be considered.
Appendix 2 should really be in the document itself rather than as an Appendix right at the end.
I think most of your comments fall into the HOW as-built information is best delivered, which will be discussed in a series of TEAMS Workshops starting on the 21st October at 11am.
If anyone wants an invite, email me at george.stevenson@BIM-in-AM.com,
On the “checklist” pont, the industry has an many such lists that may be diligently “ticked off” but the evidence is that handover information is stil poor. Your point about the longevity is well-made but again, that falls into the HOW camp.
Anonymous
20 days ago
Guidance exists to reduce uncertainty. Whilst supporting the aims of the process, my concern is that readers with different interests will all believe the document supports their different positions. Is it possible that the document risks creating uncertainty rather than reducing it. It may be that a further phase will resolve this, but could also risk further uncertainty in the need to consult an additional document to get to the crux of the issues faced by industry.
Anonymous
20 days ago
While the focus of the guidance on explaining “what those operating a building need by way of information they can trust” and “what information is needed” is welcome, the lack of a clear, concise definition of ‘as-built’ information, i.e. what it is, how it should be recorded and by who limits the value of the document. The document acknowledges “differences of opinion, across the built environment sector, as to the meaning of the phrase ‘As Building Information‘” and states that “this guidance document has been developed in order to remove doubt as to the meaning of the commonly used expression ‘As-Built‘”. In my view the guidance fails to do this, and does not clearly and explicitly address the definition of ‘As-Built Information’, either in respect of identifying the root causes of differences of opinion regarding the definition or proposing potential strategies or solutions to address these. Is as-built information the final construction issue information produced by the design team; the information approved by the relevant building control authority; the construction information produced by the manufacturing, construction and installation team; a documented record of as-built construction completed on site; or potentially a combination of these?
I concur with comments below, insofar as the document suffers from being too lengthy, which is off putting, but more importantly, results in key messages being lost. Readers may benefit from information being reorganised and signposted to specific industry sectors/participants e.g. guidance for client, designers and contractors and/or approaches to information management/collection/verification at specific work stages, ideally structured to reflect a commonly used plan of work.
The guidance is not explicit that to achieve the proposed outcomes requires a significant change in mindset for a large proportion of the industry and is weaker for it. The shift in responsibilities necessary will require considerable investment in time and resources, including an industrywide commitment to training those responsible for planning, preparing, managing and monitoring the information required – potentially including the development of a register of competent clerks of work. However, making headway in this respect is unlikely to happen unless/until there is a clearer definition of what ‘as-built’ information means in practice, and there is industry consensus regarding who is best placed, i.e. competent, capable and resourced, to prepare this.
The guidance on page 11 comes closest to addressing the core of the problem, but fails to address the root causes of why the information proposed is not commonly prepared or provided. For example, referring to “drawings or models showing the final built state” – who in the project team is capable of producing this (i.e. has the ability to prepare the models and has sufficient site presence to have the necessary oversight of the construction operations) and who is going to pay for it? Likewise “final information handed over must represent what is actually built” – again, who in the project team is capable of doing this? The guidance fails to address this, which is fundamental to tackling the barriers that currently exist to collecting, recording, verifying and delivering such information.
The guidance “highly recommends” that the document is referred to “as part of the legal contract agreed” between parties. I strongly disagree with this. The guidance does not identify clear duties and obligations that would be suitable for use in contract. As currently drafted the guidance would create ambiguity and confusion regarding contracting parties’ obligations and liabilities. If the intention were to support contractual arrangements, which I am not convinced it should do, the guidance ought to include a section that specifically drafted for this purpose, providing legal guidance and or template drafting for use in contract.
I support the aims of the guidance, but ultimately feel the end-user perspective needs to be balanced with the delivery team perspective, acknowledging and addressing current barriers that exist to the production of the information end-users require. I do not believe any project team sets out to provide unreliable or incomplete information for end-users, but current procurement arrangements and expectations do not lend themselves to supporting the behaviour change required to address what is an industry wide problem. To tackle this and to be adopted by industry, the guidance needs to be more concise and specifically targeted at its intended audience.
Dieter Bentley-Gockmann, EPR Architects
Anonymous
21 days ago
I’ve reviewed the guidance and, overall, I support what it’s trying to achieve. We rely on accurate building information to manage our buildings safely, plan maintenance and improvement works, and meet our responsibilities as a building owner. I agree that information requirements should be identified at the start of a project, checked as works progress and updated at completion so they accurately reflect what has actually been installed.
That said, I think the document is longer than it needs to be and repeats some of the same messages throughout. For smaller contractors and routine work in occupied homes, it could feel quite overwhelming. A shorter main document, backed up by simple templates and practical examples, would make it much easier to follow. The requirements should also be proportionate to the scale and risk of the work. Replacing a minor component shouldn’t attract the same level of documentation as a major refurbishment or safety-critical project in a higher-risk building.
I also think it would be useful to include some practical tools in the appendices, such as a simple handover checklist, an evidence register template and a responsibility matrix. These would help organisations apply the guidance consistently, particularly on smaller projects. Examples based on typical housing work, such as fire door replacements, window replacements and fire stopping projects, would also make the guidance feel more relevant and easier to put into practice.
One of the strongest aspects of the guidance is its focus on the people who will actually use the information once the project is complete. The message that information should be planned and collected throughout the project, rather than pulled together at the end, is clear and sensible. From our experience managing residential buildings, particularly more complex and higher-risk buildings, minimum statutory information is not always enough to support effective long-term management. The emphasis on maintenance records, commissioning information, fire safety documentation and other safety-critical records reflects what building owners genuinely need. The sections covering concealed works, fire stopping, structural information and other critical building safety elements are particularly useful.
I do think some sections could be simplified. The themes of project planning, information quality, verification and client requirements appear repeatedly throughout the document. These are important points, but reducing some of the duplication would improve readability and make the guidance more accessible, especially for smaller organisations and non-technical clients.
There is also an opportunity to include more real-world examples or short case studies. Showing what a good information handover looks like for a small refurbishment, a fire safety project, an M&E replacement scheme or a higher-risk residential building would help people understand what is expected and apply the guidance more consistently.
Finally, while the guidance promotes a proportionate approach, some smaller contractors may still see the requirements as quite demanding. Including a simple minimum-information checklist for lower-risk projects, along with more diagrams, flowcharts and summary tables, would make the document easier to navigate and help users quickly understand the key requirements.
Anonymous
21 days ago
The key aspect of the naming conventions and level of information required is that this needs to include the requirements of the organisation who will end up managing the building. Otherwise all that happens is the handover documents will sit in a folder somewhere and will be pulled out only when someone needs to do dep dive work to identify why something went wrong in the building. It’s like a publishing house producing a comprehensive book of the works of Shakespeare in German, and expecting someone in England to use it to put on a play.
Neil Yeomans
Hi Neil – I absolutely agree. That is phase two which kicks off in October with meetings to try and determine the HOW.
Anonymous
21 days ago
Many thanks for forwarding, George. Admittedly I am time poor but a few comments / observations.
Have The Higher-Risk Buildings (Keeping and Provision of Information etc.) (England) Regulations 2024 been considered? I cannot find it referenced in the draft. Whilst I accept the work deliberately zooms out beyond HRBs, for completeness I think it should be referenced (particularly Schedule 1).
On that subject, I welcome the decision to zoom out (which we touched on in the original business case discussions) . I have thought for a long time that the ‘golden thread concept’ should be applied proportionately to any scheme. The draft is right to frame the question around what information is proportionately required for the safe and successful operation of an asset, rather than around the discharge of individual regulatory obligations.
As-built information has been a point of discussion for many years and a source of frustration in practice. People have genuinely read “final construction issue” and “record drawings” as meaning as-built.
Over the last nine plus years, where property owners have had cause to carry out building safety investigations, the record has been either missing or unlocatable and when found it more often than not accurately reflected what was actually built. That is before dealing with the discipline needed to keep information current through the occupation phase and the ‘changes’ a building undergoes. Removing the ambiguity in the term is a necessary first step.
The HOW will be difficult! A significant element of the HOW is producing an output with sufficient detail for those instigating the work. But before that, the WHY has to be sold to those holding the purse strings, meaning asset owners and operators. (which is why it is so great to see many who fall into that category in the list of supporters / contributors!)
We flagged in 2024 that OPEX requirements are not cascaded down the supply chain, because the end user does not fully understand them, cannot communicate them, or is focused on immediate CAPEX.
Marc Bradfield
NCG
Anonymous
22 days ago
Is the document aimed at the entire industry? If so, I am not sure that those at the smaller end of the scale will see this as being a proportionate read to identify what they should do at the end of a project? It is very long.
Hi – yes, you are right that it is a long document but as we worked through it with over 100 firms contributing, we needed to cover the various differen aspects.As a fellow SME, what we need to know is how to comply and that will be covered in the next series of workshops covering the HOW.
If you or anyone would like an invite, email george.stevenson@BIM-in-AM.com
bit concerned with the wording of as builts and no clear and concise definition who provides and limitations. we as architects do not provide as-builts but final record issue information and think this needs clearer definition within the document to avoid interpretation otherwise?
Why are the emojis in the comments so massive? It makes it difficult to read the comments.
Anonymous
27 days ago
The ITFG As-Built Requirements draft is a well-intentioned effort to improve the consistency and quality of information delivered at project completion.
However, in its current form, it risks doing more harm than good.
The document does not establish a sufficiently clear and concise definition of what constitutes as-built information and instead blurs the boundaries between as-built records, handover / O&M information, BIM processes, asset management requirements, inspection and test plans, and broader validation activities.
This scope drift creates ambiguity for dutyholders and information authors, increasing the likelihood of inconsistent interpretation and implementation.
The draft could also lead to different organisations interpreting requirements in different ways, reducing rather than improving consistency across the industry.
Without a concise, clear definition of ‘as-built’ teams will produce large volumes of unnecessary information, clients will receive documentation that makes it harder to understand the completed building, and contractual disputes will occur over what information is actually required.
A more effective approach would be to define as-built information clearly and narrowly as a record of the completed physical building, with a SEPARATE guidance covering handover requirements, O&M information, asset management, and validation activities.
This would improve clarity, reduce duplication, and encourage more consistent adoption across the industry.
Anonymous
27 days ago
There is a lot of information handed over at the end of a project – not all of it what the industry would define as ‘as-built’. The document recognises this to some degree in the content, but retains the title -as-built’ which I think is a bit confusing as the section on ‘as-built’ is actually quite small and does not deal with the practical difficulties experienced in its definition and preparation.
I would argue that the handover information should include reliable and accurate as-built records. If some of information cannot reasonably and practically verified, then that should be classified as “un-verified”
Anonymous
27 days ago
Whilst the intent of the document is good, it is very long and repetitive – if it is aimed at the ‘whole of the industry’ it needs to be much shorter and more succinct, to make it more accessible and the ‘go-to’ guide. There is a lot of ‘history’ and background explanation in it, which if it needs to stay could become a short statement at the start explaining the need for the guide with more detail in an appendix, leaving the body of the document for the practical information which is getting lost at present.
Hi Richard – I have just emailed it. Regards – George
Anonymous
28 days ago
Looks good – I will review this in relation to compliance and handover, and alignment to government soft landings (covering both the information requirements and technical assurance). Please email me a copy to michael.bracken@gpa.gov.uk
Posted by George Stevenson from a linkedin exchange with Mark Austin
Mark – George great work as always, maybe the challenge lies in ‘practical completion’ in JCT as opposed to ‘completion’ in NEC and FIDIC ICheme in infrastructure projects the handover and completion provisions can be very extensive including as-built information. This included on one project not receiving a Take Over certificate because of 2 missing as-built drawings
Posted by George Stevenson from a linkedin exchange with Joe Wharton – Creating bespoke waterproofing solutions across the commercial / industrial/ public /health and education sectors for both New Build & Refurbishment projects. E: Jwharton@garlanduk.com
Joe – Charlotte Brogan (ACIOB) I have seen so many occasions of people not visiting site during works and providing quality assurance.
We go out twice a week and document the works and provide a report which is crucial in my opinion to transparency, quality, and accountability
Posted by George Stevenson from a linkedin exchange with Charlotte Brogan (ACIOB) Senior Design and Technical Manager at Fortem
Charlotte – Brilliant piece of work, George Stevenson.
Having looked over the CLC / BIMinAM consultation details, focusing phase one entirely on what asset teams actually need is exactly the right starting point.
From a design management and document control perspective, the “how” requires a complete process shift. A true “as-built” relies on taking the contractor’s real-time site updates, paired with the site manager’s verified red-line drawings, to accurately update the master design information. Crucially, this validation must happen progressively—one work package at a time—rather than a mad rush at the end of the project.
To achieve the data integrity this guidance could benefit from the following statement; “Principal Contractors must contractually ensure designers are scoped to physically visit and audit the site during RIBA Stages 5 and 6.” If designers aren’t progressively on site verifying package completions alongside site managers, we cannot provide clients with the absolute clarity and trusted evidence that the Golden Thread demands. Looking forward to seeing how the next round of workshops tackles delivery!
Posted by George Stevenson from a linkedin exchange with Peter Cholakis
Peter – The problem isn’t a lack of technology. It’s what that technology has been asked to do.
Real progress in facilities management doesn’t start with a platform selection. It starts with process redesign: mapping how work actually flows, identifying where steps exist out of habit rather than necessity, and defining what “efficient” should look like for a given portfolio before technology gets layered on top.
Once that foundation exists, technology’s role becomes exactly what it should be — an enabler. It can consistently deploy the right processes, retain the knowledge that makes those processes work, and monitor performance against meaningful benchmarks rather than vanity metrics.
Posted by George Stevenson from a linkedin exchange with Ivan Young – Principal Designer (Building Regulations) | Author of the Gateway Bibles | Gateway 2 and Gateway 3, board-level strategy then the appointments underneath it | Competence assessed against the work
Ivan – I am not sure this is as unresolved as the discussion suggests. As built information already has a definition.
The regulations require plans showing that the work as built complies, and require the information to be handed to the person who will hold it. On higher risk buildings that is settled, and nobody needs a workshop to discover what it means.
They also answer your question. Nobody certifies what they did not verify, because the person who made the change records the change, before it is made, with the affected documents revised.
Do that and the as built is a by-product rather than a deliverable anyone attests to at the end.
And I would note where the resistance is coming from. The firms worried about the implications for them and their insurers are not worried about the definition. They are worried about being asked to evidence what they built.
George – Ivan Young – that is what people SHOULD be doing but it is clear that most are not doing so – and in the absence of those updated drawings and records, the client often gets a large number unverified drawings and schedules.
The industry clearly needs to change in light of regulations and potential enforcement but I feel we need to do it step by step and getting an industry-wide consensus of what “as-built” should include is one such step
Ivan – I disagree. Everybody understands what as built entails. If it isn’t provided to the regulator the application should be rejected. Understanding what as built means is not some higher level of understanding, it’s basic 1st year student content. Exploring new ways to counter the process serves nobody.
AS-BUILT INFORMATION, WHERE IT ACTUALLY SITS
SI 2023/909 reg 40(2)(c). The operative requirement. Such other plans as are necessary to show the work complied with all applicable requirements. A test, not a list. It never uses the words as built.
Reg 40(2)(d) to (f). Agreed documents, change control log, compliance declarations. reg 38(1) to (3). Handover to the relevant person by completion, filing structure retained, receipt acknowledged as sufficient.
38(5) defines it back to reg 40, so it carries no independent list.
Reg 31(2)(a) to (h). Properties of the information, not its content. Electronic, transferable, accurate, readable, available on request, secure, change logged, consistent.
Building Regulations 2010 reg 38. Fire safety information. Erection, extension and relevant change of use only. Not material alteration. Approved Document B vol 2 s19 and vol 1 s17. The only itemised list. Essential, plus additional for complex buildings. Guidance. BS 8644-1:2022 for structure.
We are once again attempting to change the new regime to suit old patterns and work methodology. we cannot cherry pick through the instruments to find the best fit, the documents should be read completely.
George – Thanks for the detail Ivan.
If everyone knows what should be delivered, why do so few projects delivery complete as-built drawings?
Historically, architects were commissioned to do them informed by contractors redlining where things had changed.
That no longer happens but it seems that many projects dont do what you and I agree they should.
You are much more experienced in this than me so will have seen many more projects on the ground.
Are you saying that all the detailed MEP drawings have been 100% updated with the actual installation details?
Posted by George Stevenson from a linkedin exchange with Karen Bashiyants Director-Level Digital Construction Leader | Strategy, Methodology & Project Delivery | AEC
Karen – George, spot on. The gap is organizational before it is technical: as-built verification fails when nobody owns the evidence chain connecting design intent to construction reality.
Without clear responsibility for who creates the evidence, who verifies it, and who has authority to reject incomplete records, the process eventually pushes designers toward confirming conditions they cannot reasonably evidence.
How do you see the industry closing this accountability gap?
Posted by George Stevenson from a linkedin exchange with Marc Bradfield FCIOB – Director – Nucleus Compliance Group Ltd
Marc – your challenge point above “the suggestion that as-built information and handover information should be treated as entirely separate deliverables.”
I could not AGREE more.
Teams often become hyper focussed on ticking (often regulatory) boxes, with little understanding and fail to consider what is actually needed for a safe and successful building.
George – Thanks Marc. Your background and experience makes your contribution particularly valuable to us.
Posted by George Stevenson from a linkedin exchange with Charlotte Brogan (ACIOB) Senior Design and Technical Manager at Fortem
Charlotte – I am unable to make tomorrow’s meeting however my insights are as follows;
The answer lies in moving away from broad, retrospective sign-offs and shifting toward a targeted three-pronged compliance ecosystem:
1. Structured Primary Evidence: Works partners must capture live, geo-tagged, and time-stamped digital photographic evidence at the coalface during installation, backed by marked-up red-line drawings updated weekly & not left as a handover afterthought.
2. Risk-Proportional Design Audits: Instead of asking the design team to certify blindly, we enforce package-specific audit thresholds. For instance, the design team performs physical site audits on a minimum of 25% of Facades and 10% of Kitchen Installs. They aren’t signing off on everything; they are verifying a statistically robust sample size.
3. Strict RIBA Stage 4 Baselines: Any deviation from the signed-off RIBA Stage 4 design discovered during these audits must be formally logged, escalated, and redesigned or accepted by the principal designer before work proceeds.This shifts the burden from “unreasonable certification” to a verifiable trail of factual, sample-audited data.
Posted by George Stevenson from a linkedin exchange with Gavin Edwards – Experienced Architectural and Construction Specialist at GE Consulting
Gavin – Designers shouldn’t produce “As Built” information
George – Yet that is often what clients are given in their handover information
Gavin – it would just be the last construction issue by the consultant – you’d never go back to site and update your drawing to match what you found had been constructed – as built information is prepared by the contractor as his construction progresses
George – if only that really happened. I agree that it’s not the responsibility of the designer – but that is often what we get. As can be seen from the survey we did last week.
If you know of contractors who actually ensure all the drawings are truly “as-built” please ask them to contact me.
There must be a unicorn out there somewhere
Gavin – there’s meat here for a significant debate but if you call something As Built and your Services say thats what you’ll provide then the Client has every right to expect just that – I always delete As Built because I know it is not possible for a designer to provide that – I’m surprised that there’s not been more comments on the topic – a good subject though so 10/10 on your post…
George – Thanks Gavin. I think the important thing is for clients to understand the process of procuring buildings and services will need to change if they really need all of the drawings to reflect what was built.
I am not convinced that is necessary for ALL record drawings. We should prioritise what is really important and what is nice to have. Also have a status of Verified or Unverified.
Gavin – I agree totally but a cold beer needed
This comment is posted by george stevenson but originated from Duncan Howie an expert in Smart Buildings
Duncan – the data’s there; let’s use it –
Maybe not directly relevant, but, if nothing else, could designers be obliged to understand changes and incorporate learnings into future designs?
This comment is posted by george stevenson but originated from David Shepherd from Houses of Parliament project.
David – Thanks for this thoughtful post. The distinction between record information and verification of installed reality is important.
A designer’s final construction issue information may be entirely correct as a record of design intent and approved changes, without constituting evidence that the asset was installed exactly as shown.
What stands out for me is the reference to “the level of verification that has been applied”, but that naturally raises a further question: “when was that verification performed, and what evidence supports it?”
Many asset attributes can only be captured during a limited evidential window (e.g., installation and commissioning).
If identity, location, commissioning status or compliance evidence are not captured while directly observable, the industry often has little choice but to recover, infer or reconstruct the information later.
Surely, the next step is not just distinguishing between design information and installed reality, but also between information that is observed, derived and inferred.
The missing step is to define evidence capture during the evidential window as a contractual deliverable, not merely as handover documentation.
End of comments received directly by A Taylor…………..
As part of the draft consultation, I would offer the following observations:
The ancillary issues that the guidance touches on are important, but should not be included in this note as they are already extensively covered in other guidance.
Similarly, many elements of the draft could be split out into a separate ‘handover and O&M definition’ document – this would allow the as-built definition to be concisely and cleanly defined.
Is there room for the working group to take time to take stock of the current comments and restructure the document?
Before we started the working group to define what “as-built” means, one of the contributors suggested we use the Oxford English Dictionary definition.
“The adjective “as-built” describes something that shows the actual shape, size, condition, or structure of a building project or design just as it was finished, rather than how it was originally planned.”
Given that few clients are construction professional and might expect plain language to describe what they should expect, perhaps we should agree that is the required outcome and focus our discussion on the more complicated stage of HOW it can be done – or tell clients it isn’t possible.
—-Speaking as a building control professional, I feel it is critical that the document is circulated directly to the organisations who represent the profession, both as individuals and building control bodies. The guidance could be read as instructional for RBI’s and BCB’s, and Section 12 is quite detailed. Who has provided input to list the ‘what an RBI should reasonably be expected to check’ section for example? I understand the aims of the guidance, but I’m concerned that without direct consultation the effectiveness of the document will be reduced.
There are also some clearer distinctions to be drawn out in respect of the term ‘as-built’. There are clearly differences between those elements required by legislation (and the differences for building types / work) and those elements required by contracts. Conflating the two will cause some confusion as they are very different things. In particular ‘as built plans’ will have two distinct meanings. For HRB’s there is a direct legislative requirement for this within the completion certificate application but this is not replicated for non-HRB’s.
I’m happy to make my own comments as a building inspector, but I can’t speak on behalf of organisations obviously.
I would recommend that before anything is progressed, input is sought directly from organisations such as LABC, ABCA, ARBI, CABE, RICS for example, on the issues relating directly to the building control function. Unless they are already involved, I doubt whether a response will be received by the 16th October.
Hi George,
I hope all is well. I have had a quick read and made some comments below. Some of which may be completely irrelevant.
Overall, the document represents a significant and positive step towards establishing a common industry understanding of what information should be delivered at handover and how that information should be verified, validated and managed throughout the lifecycle of a building. It addresses many of the historic shortcomings that have resulted in inaccurate, incomplete and unreliable building information being transferred between project teams, owners and operators. The emphasis on building information as an asset, together with the recognition that information must be planned from project inception rather than assembled at completion, aligns well with the principles underpinning the Building Safety Act, the Golden Thread and modern asset management expectations.
The document is particularly strong in establishing the need for accurate records of what has actually been built, rather than reliance upon design information and isolated change records. Its recognition that operational building users require information that remains understandable and usable over many decades is one of the strongest themes running throughout the draft. The distinction between As-Built Record Information, Building Information for Operation and Additional Client Asset Information provides a logical framework that is likely to improve consistency within future handover documentation. The requirements for verification, validation, evidence traceability, commissioning information and clear identification of safety-critical elements are all appropriate and consistent with post-Grenfell expectations. The emphasis placed on concealed elements such as fire stopping, structural connections and embedded services is particularly welcome given the difficulties repeatedly encountered in existing buildings where these elements are either undocumented or inadequately recorded.
From a building safety perspective, the document successfully captures many of the information management principles introduced through the Building Safety Act and associated regulations. It references Regulation 38 information, Golden Thread requirements for higher-risk buildings, dutyholder responsibilities, completion certification requirements, commissioning evidence, and the broader concept of information assurance. The guidance is therefore well aligned with the direction of travel of the Building Safety Regulator and the wider industry.
However, whilst the document is strong as a statement of principles, it is noticeably less developed as an operational standard. A recurring issue throughout the guidance is that it defines what good information looks like conceptually but does not define sufficiently what evidence is necessary to demonstrate compliance. The document frequently states that information should be verified, validated and trustworthy, yet it does not provide a consistent acceptance framework defining when information is considered acceptable or unacceptable. In practice, two competent reviewers could assess the same handover package and reach entirely different conclusions while both claiming compliance with the guidance. There is no clear threshold for missing information, incomplete records, conflicting evidence, or legacy information gaps.
The guidance also places substantial reliance upon clients defining information requirements at the outset of projects. Whilst this is sensible for sophisticated clients with established asset management teams, many clients, particularly smaller organisations, and housing providers with limited technical resource, may not possess the knowledge necessary to specify appropriate requirements. Although the document acknowledges this problem, it provides limited practical assistance. The inclusion of standard information schedules, example specifications or worked examples would significantly improve usability and reduce the likelihood of inconsistent implementation across the sector.
A further concern relates to legacy buildings and refurbishment projects. Much of the guidance appears to assume that comprehensive records either exist already or can be readily obtained. Many existing residential buildings, particularly older stock, contain substantial gaps in information regarding compartmentation, structural detailing, concealed services, cavity barriers and historic alterations. The document does not sufficiently address how uncertainty should be managed where information cannot reasonably be obtained without extensive intrusive investigations. Nor does it establish confidence levels for information based upon its source, age or reliability. I may have missed something but this appears a significant omission given that uncertainty management forms a substantial part of fire and structural risk management in existing buildings.
The guidance also appears to focus heavily upon the creation and transfer of information but is less developed regarding the management of that information throughout occupation. While references are made to ongoing updates and change control, there is little discussion regarding information degradation, data governance and the practical realities of ensuring that records remain accurate throughout the life of the building. From my experience, information often becomes unreliable not because it was inaccurate at handover but because subsequent alterations, maintenance activities and operational changes are not adequately recorded. More emphasis on information stewardship during occupation would strengthen the guidance considerably.
From a Building Safety Act perspective, the document should not be regarded as a complete representation of the regime. Whilst Golden Thread information and handover requirements are addressed extensively, there is very limited consideration of safety case development, resident engagement obligations, mandatory occurrence reporting, building assessment activities or wider occupied building duties applicable to Accountable Persons and Principal Accountable Persons. The guidance should therefore be viewed as an information management framework rather than a comprehensive building safety compliance document. Sorry if I have misunderstood this.
Of relevance from a fire safety standpoint is the limited treatment of BS 9991 and BS 9999 management assumptions. The document focuses strongly on physical assets, installed systems and compliance records but is considerably weaker regarding the management arrangements that underpin many fire strategies. Both BS 9991 and BS 9999 rely heavily upon assumptions regarding occupancy, management controls, maintenance arrangements, staff responsibilities, emergency procedures and ongoing operational management. Whilst the guidance requires fire safety information and operational information to be transferred, it does not explicitly require the handover of management assumptions, fire safety management plans or strategy assumptions registers. This is especially important within mixed-use developments where the interaction between residential, retail, office and ancillary occupancies form a fundamental part of the fire engineering solution. A future building operator may understand what was built but remain unaware of how the building was intended to be managed.
Similarly, whilst fire stopping records, fire door schedules, commissioning records and cause and effect documentation are appropriately addressed, the document places surprisingly little emphasis on the fire strategy itself. There is no strong requirement for an approved final fire strategy, records of departures from the strategy, validation of key assumptions or retention of supporting fire engineering assessments. Given that the fire strategy often represents the primary document explaining why safety measures exist, this omission is notable.
Overall, the document is a well-considered and valuable contribution to improving industry practice. It successfully addresses many longstanding deficiencies in handover information and represents a significant advance on traditional interpretations of as-built information and O&M manuals. However, it remains fundamentally a framework document rather than a definitive acceptance standard. To become a truly authoritative industry reference, further development is required around information acceptance criteria, evidence thresholds, management assumptions, safety case interfaces, treatment of legacy buildings and the practical application of BS 9991 and BS 9999 management requirements, particularly in mixed-use and higher-risk residential buildings. In its current form, I would regard it as an excellent statement of intent and a robust foundation for future industry standards, but not yet a complete or standalone benchmark for determining whether a building information package is adequate for long-term occupation, management and building safety assurance.
Sorry if I have misunderstood the criteria.
Regards,
Dave
Hi Dave – thanks for your detailedand well-considered contributions. I agree with everything you have suggested and these are the topics we will be discussing in Phase Two – the HOW – starting on the 20th October at 11am? the commenting is anonymous so If you can make that email me at george.stevenson@BIM-in-AM.com and we will send you an invite.
—George, here are my comments and recommendations.
In the introduction you talk about all the reasons why this is important, including efficiency. Efficiency can mean many different things, all of them positive. However, money gets everyone’s attention so I would add: resulting in improved profitability for the building owner and occupants throughout the building lifecycle.
You talk about handover at the end of any project. It might be more helpful to emphasize the goals of this initiative if you instead talk about the transition from the construction phase to the commissioning and operational staff. Make it look like a continuum with different organizations involved. Not an ending. In many other places you talk about the conclusion of a project. I’d recommend that whenever you can you use this same transition terminology instead of conclusion. This makes it sound more like a part of the building lifecycle, not the end of something.
You get to the bottom of page 4 before you state:
• Both new build and work on existing buildings.
This is important enough that I would recommend stating this up front as a part of your introductory statements, even if it becomes a duplication. There are contractors who specialize in retrofits and upgrades. They could easily assume that this does not apply to them when you read the previous pages. It all sounds like the focus is new construction.
I would recommend that in section 5 as a part of verification and validation process that you call out the Commissioning step and require that the commissioning agent confirms that all live systems (BAS, lighting, security, fire, etc.) agree with and accurately reflect the as-built drawings before releasing the contractor from their obligations. This not only confirms accurate and reliable data on day one but sets the stage for keeping them in sync as the building continues its lifecycle.
In your BIO section I recommend that you include conformance to all industry or government standards for systems providing live data. Obviously, I am thinking of BACnet for live building automation data but there are standards for most subsystems. When ownership of a building changes part of the required deliverables should be identifying any cases where this is not true. In my example this would allow the new owner to introduce analytics or FDD value-added applications to improve building operational efficiencies. You want to avoid the surprise of needing to do a rip-and-replace of building systems without prior knowledge of that being necessary.
I am not sure where this belongs but somewhere it should be stated that all building data is the property of the building owner. It is not allowable for a contractor, or one of their suppliers or subcontractors, to lock the building owner out of access to the as built or real time data for the building.
The contractor should not be allowed to just walk away from a project. There should be a substantial warranty period for which they are required to provide any information that was legally required and they omitted from project deliverables.
—–As a Safety Officer, I believe that health and safety information should be an essential part of the handover documentation. It should include:
– As-built drawings showing safety-critical systems and installations.
– Fire protection and emergency arrangements.
– Risk assessments and safe operating procedures.
– Inspection, testing, and maintenance records.
– Relevant safety information for future maintenance and operations.
Providing accurate and complete safety information at handover will help building owners and operators manage risks effectively throughout the building’s lifecycle.
Thank you for the opportunity to contribute.
Yes – I fully agree but we expect to cover that in the HOW workshops. which start on the 20th October at 11am? the commenting is anonymous so If you can make that email me at george.stevenson@BIM-in-AM.com and we will send you an invite.
——-Kevin added a whole document that needs review too …Overall, I believe this is a very valuable piece of industry guidance. The five guiding principles, in particular, and the “trust vs. usability” framing in Section 7 are both insightful and highly relevant.
While reviewing the document, I noticed a few points that I felt would benefit from further consideration, along with some minor areas where additional polishing may be helpful. I thought it would be useful to bring these to your attention before the document is finalised.
Please find attached a PDF highlighting the points for your review and consideration.
Apologies but I don’t think we have received your PDF document. Can you email it to me at george.stevenson@BIM-in-AM.com and we will also send you an invite to the HOW workshop on the 20th October.
—-Suggested omissions include;
Without the above the building operator maintainer can not start understand what has changed from the design intent and the work arounds required to keep the occupants safe.
Note that the approach by CLC and the above comments relates to BR requirements and not CDM2015 requirements.
The CDM 2015 requirement is suggested to be for an As-Built ‘access and working space drawing’ showing vehicle and pedestrian routes around the site and structures, access to below ground services, access to services inside and outside the structure, locations for access equipment, cranes and emergency response vehicles. The drawings need to show all installed plant, equipment fittings and fixtures and the access space around them and warnings where work equipment is required to access / reach a working space. These drawings are also suggested to identify locations where services are isolated.
—–MD of smoke control subcontractor SE Controls, was particularly positive and said the timing was perfect because he is leading a standards group for smoke control and he said what they are releasing seems to align well.
It’s a big document to consume, so I asked ChatGPT to produce a summary.
It looks quite good to me and I plan to issue this to my contacts.
Is it OK from your perspective?
Suggested omissions include;
Without the above the building operator maintainer can not start understand what has changed from the design intent and the work arounds required to keep the occupants safe.
Note that the approach by CLC and the above comments relates to BR requirements and not CDM2015 requirements.
The next tranche of comments have been received directly by Anthony Taylor and are transcribed/copied across to this record for the purposes of ‘The Record’ being in one place and to facilitate analysis.
We fully support the requirement to provide accurate handover information, however the guidance as currently written is overly prescriptive and too open ended. The guidance purports to outline the minimum level of information, however, also suggests that clients should be able to request any additional information they require. The document is likely to be included in future contract requirements and therefore needs to be very clear about what is the minimum and optional extras, which will invariably have a cost implication. If not clarified this could delay handovers and impose a significant additional burden on the project delivery teams. In discussion with our consultants it is clear the level of verification of information will not be possible nor is it their understanding or indeed the intention of any regulations.
See below comments to individual sections.
Section 1: Purpose of this guidance
1.1 As noted above there reference to minimum content is not correct noting references elsewhere in the document (See 9.1), which intimates the provision of whatever information the client requests if not defined at contract stage.
Section 2: Scope and intent of this guidnace
1.2 The guidance notes the aim to clarify the meaning of ‘As-Built’ information to provide a reference for both Building Control bodies, Third Party Reviewers, Contractors, Clients, etc.
Its is worth noting the requirements under the Golden Thread will differ from the requirements under for the other interest groups. The guidance needs to set this out clearly to avoid confusion at project level.
Section 3: Contractual and legal considerations
1.3 No comment
Section 4: Acknowledgements
1.4 The absence of the major residential developers on the list of collaborators is unfortunate.
Section 5: Key principles
1.5 No comment
Section 6: What information we are referring to
1.6 We disagree with the statement that ‘final design for construction’ documents are ‘NOT PRACTICABLY USABLE’ by building owners and not acceptable under the proposed guidance.
It is our experience that drawings first need to be updated prior to construction works and should therefore reflect what has been constructed. The Principle Designer will review the information prior to handover and provide a statement that this represents an accurate record of the building as-constructed.
Section 7: The key attributes for as-built information
1.7 It is noted that the level of information may exceed the level required to obtain regulatory approval with example given of performance specifications. Again this is not our experience as a performance specification will stipulate the detail design requirements to be provided by third parties prior to regulatory approval and handover.
1.8 The guidance proposes intrusive access ‘where appropriate’ to check life safety systems as part of the handover process. This seems an extreme requirement noting inspections and first of kind installations can be reviewed and recorded throughout the project duration.
1.9 There is also a requirement for an ‘independent witness’ for life safety systems. There needs to be a definition of independent as this has the potential to create an excessive burden on the project.
Section 8: definition of specification
1.10 The guidance requires a record of information which is unverified or unverifiable. More detail is required to understand the potential scope for the this requirement.
Section 9: Minimum levels
1.11 The guidance requires information to be conveyed in a format that a lay person could easily understand. The level of detail stipulated elsewhere in the requirements will make this difficult. Rebar detailing and structural calculations are unlikely to be easily interpreted by lay people.
1.12 Levels of detail should be agreed prior starting the project. This is not always possible as buildings may only be sold to a new owner midway through construction.
1.13 The requirement to record any work not complaint with regulation at handover stage does not make sense. Surely buildings would not be handed over until regulatory compliance is achieved?
1.14 The statement that the default position would be that he client is entitled to provide any further information if not agreed otherwise is unfair. Again should this guidance not be looking to set a minimum? Any additional information can always be requested at contract stage as this will cost implications.
1.15 ‘For concealed or embedded elements (structure, services, fire stopping), the record must be sufficient to locate and properly identify the product/item without destructive investigation.’ This is not possible for elements like steel re-enforcement.
1.16 Design calculations to prove regulatory compliance as a stated requirement is not currently provided and will involve a vast amount of additional information, which will presumably also need to go through the verification process at handover.
1.17 ‘Independent verification’ need to be more clearly defined as open to interpretation.
1.18 Safety critical elements is noted as needing inspection and verification by the professional responsible for designing the element. This will require cost additional inspection regimes from the appointed consultants for something competent project managers should be able to complete.
1.19 Reference to other guidance documents are noted in 9.6. This appears to move beyond the intent of defining minimum requirements.
Section 10: Guidance specifically for clients and building owners
1.20 The guidance recommends that end users can demand information in excess of pure statutory requirement. Again this appears to go beyond a minimum requirement as per the stated intent in the introduction.
Section 11: Illustration of information requirements collation across building lifecycle
1.21 No comment
Section 12: Statutory requirements for information and the requirements
1.22 No comment
Section 13: Statutory requirements for building information
1.23 No comment
I am an ARB-registered architect who has switched to producing information-management software for the AEC sector, so I should declare a commercial position. My comment is made in my professional capacity, with the safety of the public in mind.
Two kinds of information in the handover pack
The draft rightly anchors trustworthy information in people: how it was collated, verified and validated, and by whom (section 7), and competent, independent sign-off (9.5). The provenance, traceability and signatures it asks for are valuable because a competent person stands behind them. My reason for writing is not to challenge that, nor to debate the meaning of the term “as-built”, but to point out that the pack holds two distinct kinds of information, and that emerging AI workflows threaten the competence behind one of them in a way the record itself cannot surface.
The first kind is a record of the building: drawings and models of the final state, the location of concealed items, attribute data. For these, as an oversimplification, “verification confirms the information matches what was built” works as a test, and automation is little threat where human sign-off is required, because the act of verifying is a distinct act grounded in the physical world.
The second kind is derived from documents, not from the building: key design assumptions for future modification, derogations accepted by the client, residual risk registers, outstanding issues and assumptions. For these there is no building to check against, and the requirements can say a register must exist but cannot say what must be in it; what belongs in it can only be found by reading the project record. The draft asks for traceability (9.2) and for registers to name their sources (9.6), but it does not ask anyone to read a compiled register back against the record it was drawn from, so nothing in the project’s own verification confirms that such a register is complete.
Where AI compilation will land, and what it does to the reviewer
This is important because it is the content people will want to use AI to compile, because it is the thousands-of-documents part of the pack, and as a result it is where the behavioural problems will be the hardest to guard against. The people compiling it are designers, contractors and information managers whose job is producing and passing on this information, for whom checking feels like overhead, even if necessary and critical overhead.
The AI promise of compiling with a tool and “fixing the remaining few per cent” is the path of least resistance and would be seen as welcome by many. In this context, fixing the remainder means reviewing the tool’s output rather than reading the sources, and vigilance in reviewing output is well documented to fall as the tool appears more capable, and, critically, to fall without the reviewer being aware of it. Once a certain accuracy threshold is reached, reviewer confidence increases, automation complacency increases, and review skills can atrophy as a result.
Worse, the omissions are the hardest to spot, because items the tool left out give the reviewer nothing to look at, and over time the problem compounds. The ability to notice that a register is incomplete comes from having worked through material of that kind, and if the compiling is delegated, that familiarity stops being built. The record would still carry its signature, provenance and traceability, but the competence that gives those attributes their value would have thinned, and nothing in the record would show it. Professionals aware of this phenomenon are less likely to fall for these failures, but current industry discourse is far too quiet on this and it remains a growing risk area.
Deterministic and probabilistic compilation
Whether this matters depends on how the compilation is done. A deterministic process can be tested, its errors corrected through its logic and its output reconciled against a known rule. A probabilistic one, as most current AI systems are, makes a fresh judgement on every item, so confirming that each item was compiled correctly becomes the human’s task, which is the monitoring task described above. AI run alongside an existing review reduces risk; AI run in place of the first read, with a human fixing the difference, is the direction of travel much of the industry discussion assumes and can, counterintuitively, substantially increase the human scope of a review task and make proportionate review a much muddier concept.
Three suggestions
The likely objection
The likely objection is that the source documents were already signed off by the designer or contractor. That sign-off vouches for the documents. It does not vouch for whether the register reflects them as a competent person reading the originals would have understood them. Nor are the designer and contractor immune: they may meet the same automation complacency when producing those documents, so errors missed at their sign-off pass through to every later stage. This is a conceptual problem for the lifecycle of information on a project, not only for its finalisation at handover, which is why addressing it is vital. Prompt and document injection, where text inside a source document steers or corrupts the tool’s output, is a separate and more complex facet of the same problem and not addressed here.
Further research
The phenomenon of AI omissions for professional reviewers is set out in a preprint, The Omission Gap (SSRN, 2026), and I am continuing research at the intersection of professional competence, document integrity and AI systems. I would be more than happy to discuss this further if it would be beneficial to the consultation.
You can message info@vbrief.ai to reach me.
James Wright-Zhang
Adding to the below post, see below further thoughts
Include calcs where they are needed to safely carry out future work: examples
Do not include calculations when they have no relevance to H&S; examples
A future designer does not usually need to see every page of bending moment, fatigue or reinforcement calculations. What they need is:
Ask “Would a competent engineer, maintainer or contractor need this information to safely alter, maintain or demolish the asset in the future?”
There needs to be a consideration of the production of appropriate design and design check calculations, to be provided as part of the as-constructed information. Below are some pointers.
NR standards include provision of suitable as-built drawings and design and check calculations to allow future use.
A common-sense approach is needed, with some suppliers offering meaningful packs which include key outputs of calculations where they are critical to safe future use, maintenance, alteration, or demolition,
Some suppliers produce reams of wholly inadequate outputs which are meaningless to anyone looking at them in future, hence are useless.
A test is “ Will someone need this calculation (or its outcome) to avoid risk in the future”. Guidance on what a calculation pack within a H&S file should contain is welcomed, but here is a quick summary suggestion.
“The CDM Health & Safety File should not replicate design calculations but must clearly identify and communicate all safety-critical design assumptions, limits, and constraints derived from those calculations that are necessary to ensure the safe operation, maintenance, alteration, or demolition of the asset”
Please can you email me a copy as I am finding it hard to review with the format provided.
steve.williams5@networkrail.co.uk
Network rail have clear expectations for H&S files (including as constructed drawings) in standards NR/L2/OHS/0047, and NR/L2/INF/02202. Suggest a paragraph is added referencing other such documentation or acknowledging such standards exist e.g. add thus
“This document compliments other documents. For instance, Network rail have clear expectations for H&S files (including as-constructed drawings) in standards NR/L2/OHS/0047, and NR/L2/INF/02202″
On page 4 please add a forth bullet after “It applies to” to read thus:-
Our principal argument set out in the file note we produced for delineating and defining scope of For Record Drawings is that consultant Record Information and physical verification of the completed works are different and discrete evidential functions, and should remain so. The note defines consultant information as the final coordinated design intent, updated for formally notified and approved changes, while expressly excluding continuous supervision, comprehensive dimensional verification and certification of every installed element.
What the guidance seeks to establish is a somehow all-encompassing unified record where distinction between functions seems blurred and therefore either renders responsibilities null or infers total responsibility for all aspects on a specified agent (client / PC / PD / other dutyholders), depending on how you view it, which flies in the face of the regulations key tenets of sequential responsibilities discharged by competent actors towards a holistic record – Golden Thread.
What it seems to legitimately be trying to achieve is trustworthy, usable lifecycle information.
Its difficulty is that Sections 6–9 and Appendix 1 repeatedly moves between:
Terms such as “authoritative record”, “verified and validated record information of what has actually been built”, “As-Built Drawing”, and “As Constructed Record Document” therefore risk attaching the assurance status of the whole package to each consultant-produced record drawing.
Recommended consultation position:
Retain a composite, evidence-led objective, but expressly define consultant’s For Record Drawings / Record Information as one constituent source, explicitly stating that an individual designer’s record information is not certification of the physical installed condition unless a separately scoped, competent verification service has been commissioned and performed. This may result in the light of responsibility for this information falls on the PC or client, but we don’t feel that it should as it is not necessary or supported by the regulatory framework.
What is the legislative position:
The BSA-2022 enables regulations covering certificates, information creation and retention, and inspection/testing – which taken together suggests ‘an authoritative record’, however it does not itself appoint the architect (as PD, or another design dutyholder) as universal verifier of the completed asset, which clearly is beyond their independent design scope or expertise.
There is nothing in the legislation that determines that any one dutyholder has an obligation to prove that contractors installed every element in accordance with their design.
Equally, as Pricipal Designer, the GW3 declaration is not to be worded as an architect’s certification of dimensional probity, workmanship, concealed construction or correctness and appropriateness of all installed products.
Likewise, the Principal Contractor is not require to re-survey every trade installation; the legislation determines that the PC is responsible for supporting a managed evidence chain using competent contractors, specialists, inspections and tests, in conjunction with technical and testing standards and approvals for the materials and product specified and/or controlled through the orchestrated change protocols (and records).
The BSR’s fundemental remit is to inspect the completed work and issue the completion certificate only if, after taking all reasonable steps, it is satisfied that the work complies, prescribed information is complete and accurate, and required information has been handed over. This does not constitute a requirement to insist on reconstituting all contributors inputs, across the entire and lengthy process (Stage 4-6, over sometimes.many years), into an authoritative ‘As-built’ production. Their final assessment is not replaced by a designer’s record drawing; even their Completion Certificate is evidence, but not conclusive evidence, of compliance.
The fundementals underpinned in regulation…..
There is no provision requiring the architect to certify that its drawings physically match every installed condition.
This conclusion is interpretive, but follows directly from the allocation in the regulations:
Composite traceability is the essence of the golden thread evidence rather than Composing reality….
This in essence gathers together the approved design, authorised changes, construction records, installed systems, tests, non-conformances and the accepted baseline. This is substantially the evidential suite proposed in our previous file note outlining ‘For Record’ suites of information from relevant dutyholders.
A reasonable analogy (perhaps not a brilliant one) would be that of an auditor (BSR) looking at a company’s financial report at the end of the year (post-completion) – they aren’t required to observe each and every receipt for each and every purchase, they are required to evaluate and enquire in order to satisfy themselves, taking all reasonable steps, that the book represents the actuality. The responsibility rests with the company (Dutyholders) that their report is accurate. But its the process across the year that’s important (The Golden Thread) not some retrospectively produced overarching composite record that attempts to bind every element.
strongly agree with this commentary
I agree with the central concern expressed by ATGL and other designers.
A designer’s final construction or record information should not be interpreted as certification that everything shown was physically installed exactly as drawn where the designer has neither been commissioned nor able to verify that fact.
That distinction is important.
However, I do not believe the answer is therefore to redefine “as-built” so that information describing design intent can be accepted by clients as a record of physical reality. Instead, we need to distinguish clearly between what information represents, who is responsible for producing it, and the level of verification that has been applied to it.
What does “as-built” mean?
One of the most useful outcomes from three months of discussion involving more than 100 contributors is that a seemingly simple term has exposed a much bigger industry issue.
The comments that the guidance of how the term “as-built” should be interpreted by clients and those people occupying buildings should be much (much) shorter are well made.
Here is my suggestion – from the Oxford English Dictionary
“The adjective as-built describes something that shows the actual shape, size, condition, or structure of a building project or design just as it was finished, rather than how it was originally planned.”
On that basis, a final construction issue drawing can be extremely valuable record information, but if nobody has established whether the completed construction corresponds with it, it should not be presented to the client as verified evidence of the installed condition.
That does not make the drawing wrong, nor does it make the designer responsible for verifying construction. It simply means we need to describe its evidential status accurately.
Indeed, this appears to me to be broadly consistent with ATGL’s own position: consultant record information and physical verification are different evidential functions and should remain distinguishable.
The question therefore becomes:
If the designer is not responsible for verifying the installed condition — quite reasonably in many cases — how does the industry collectively provide the client with a trustworthy record of what has actually been built?
That is the gap I believe the guidance needs to address.
The client should not have to reconstruct the building at handover
Our general consensus, and from correspondence from the ATLG is that this document is just too long – who is the intended document for?
The document really needs to be restructured into a concise actionable checklist with signposting guidance. Certainly, a case of ‘less is more’. Does this document really need to repeat core definitions, client duties etc – should it not sign post back to already agreed and issued CLC documentation? Slight irony that the document itself states the need for ‘value over volume’ and then sets this all out in a 45 page document!
There is a lack of practical realism if it thinks this document will really apply to all building work – from small domestic projects to large complex ones. Have they ever seen how a small domestic project works – getting one drawing let alone a full as-built set would be considered a win. If you make something too academic or too paperwork heavy, then the smaller / lower end will just ignore it. Would recommend there is a ‘lite’ version of this document for domestic / smaller end and the more detailed version for the larger more complex projects. There should certainly be a split between HRB and non HRB is this document – a clear split.
It doesn’t really align with our viewpoint – we still see the need for As-Built to actual be Record Information (by consultants) and Verification / Declarations (by contractors).
Where it states – ‘Those using an as-built record must be able to trust the information on or in the record’ , whilst an understandable ask -the ‘as-built record information’ is only at a moment in time. If say 10 years have passed, anything could have happened since then – therefore blindly trusting aa-built record information should not be encouraged, the information must be verified and checked prior to any works taking place even if the information is trusted.
Notes on digital information needs caveating – the building will last likely longer than any current supported platform or format, how is its access maintained…..it’s only 30 years really since floppy disks / CD-ROM’s etc or VHS – and you’d struggle to access that now.
The document is text heavy – maybe some diagrams of tables / matrix would be clearer? The practicality of this document with regards the day to day needs to be considered.
Appendix 2 should really be in the document itself rather than as an Appendix right at the end.
I think most of your comments fall into the HOW as-built information is best delivered, which will be discussed in a series of TEAMS Workshops starting on the 21st October at 11am.
If anyone wants an invite, email me at george.stevenson@BIM-in-AM.com,
On the “checklist” pont, the industry has an many such lists that may be diligently “ticked off” but the evidence is that handover information is stil poor. Your point about the longevity is well-made but again, that falls into the HOW camp.
Guidance exists to reduce uncertainty. Whilst supporting the aims of the process, my concern is that readers with different interests will all believe the document supports their different positions. Is it possible that the document risks creating uncertainty rather than reducing it. It may be that a further phase will resolve this, but could also risk further uncertainty in the need to consult an additional document to get to the crux of the issues faced by industry.
While the focus of the guidance on explaining “what those operating a building need by way of information they can trust” and “what information is needed” is welcome, the lack of a clear, concise definition of ‘as-built’ information, i.e. what it is, how it should be recorded and by who limits the value of the document.
The document acknowledges “differences of opinion, across the built environment sector, as to the meaning of the phrase ‘As Building Information‘” and states that “this guidance document has been developed in order to remove doubt as to the meaning of the commonly used expression ‘As-Built‘”. In my view the guidance fails to do this, and does not clearly and explicitly address the definition of ‘As-Built Information’, either in respect of identifying the root causes of differences of opinion regarding the definition or proposing potential strategies or solutions to address these.
Is as-built information the final construction issue information produced by the design team; the information approved by the relevant building control authority; the construction information produced by the manufacturing, construction and installation team; a documented record of as-built construction completed on site; or potentially a combination of these?
I concur with comments below, insofar as the document suffers from being too lengthy, which is off putting, but more importantly, results in key messages being lost. Readers may benefit from information being reorganised and signposted to specific industry sectors/participants e.g. guidance for client, designers and contractors and/or approaches to information management/collection/verification at specific work stages, ideally structured to reflect a commonly used plan of work.
The guidance is not explicit that to achieve the proposed outcomes requires a significant change in mindset for a large proportion of the industry and is weaker for it. The shift in responsibilities necessary will require considerable investment in time and resources, including an industrywide commitment to training those responsible for planning, preparing, managing and monitoring the information required – potentially including the development of a register of competent clerks of work. However, making headway in this respect is unlikely to happen unless/until there is a clearer definition of what ‘as-built’ information means in practice, and there is industry consensus regarding who is best placed, i.e. competent, capable and resourced, to prepare this.
The guidance on page 11 comes closest to addressing the core of the problem, but fails to address the root causes of why the information proposed is not commonly prepared or provided. For example, referring to “drawings or models showing the final built state” – who in the project team is capable of producing this (i.e. has the ability to prepare the models and has sufficient site presence to have the necessary oversight of the construction operations) and who is going to pay for it? Likewise “final information handed over must represent what is actually built” – again, who in the project team is capable of doing this? The guidance fails to address this, which is fundamental to tackling the barriers that currently exist to collecting, recording, verifying and delivering such information.
The guidance “highly recommends” that the document is referred to “as part of the legal contract agreed” between parties. I strongly disagree with this. The guidance does not identify clear duties and obligations that would be suitable for use in contract. As currently drafted the guidance would create ambiguity and confusion regarding contracting parties’ obligations and liabilities. If the intention were to support contractual arrangements, which I am not convinced it should do, the guidance ought to include a section that specifically drafted for this purpose, providing legal guidance and or template drafting for use in contract.
I support the aims of the guidance, but ultimately feel the end-user perspective needs to be balanced with the delivery team perspective, acknowledging and addressing current barriers that exist to the production of the information end-users require. I do not believe any project team sets out to provide unreliable or incomplete information for end-users, but current procurement arrangements and expectations do not lend themselves to supporting the behaviour change required to address what is an industry wide problem. To tackle this and to be adopted by industry, the guidance needs to be more concise and specifically targeted at its intended audience.
Dieter Bentley-Gockmann, EPR Architects
I’ve reviewed the guidance and, overall, I support what it’s trying to achieve. We rely on accurate building information to manage our buildings safely, plan maintenance and improvement works, and meet our responsibilities as a building owner. I agree that information requirements should be identified at the start of a project, checked as works progress and updated at completion so they accurately reflect what has actually been installed.
That said, I think the document is longer than it needs to be and repeats some of the same messages throughout. For smaller contractors and routine work in occupied homes, it could feel quite overwhelming. A shorter main document, backed up by simple templates and practical examples, would make it much easier to follow. The requirements should also be proportionate to the scale and risk of the work. Replacing a minor component shouldn’t attract the same level of documentation as a major refurbishment or safety-critical project in a higher-risk building.
I also think it would be useful to include some practical tools in the appendices, such as a simple handover checklist, an evidence register template and a responsibility matrix. These would help organisations apply the guidance consistently, particularly on smaller projects. Examples based on typical housing work, such as fire door replacements, window replacements and fire stopping projects, would also make the guidance feel more relevant and easier to put into practice.
One of the strongest aspects of the guidance is its focus on the people who will actually use the information once the project is complete. The message that information should be planned and collected throughout the project, rather than pulled together at the end, is clear and sensible. From our experience managing residential buildings, particularly more complex and higher-risk buildings, minimum statutory information is not always enough to support effective long-term management. The emphasis on maintenance records, commissioning information, fire safety documentation and other safety-critical records reflects what building owners genuinely need. The sections covering concealed works, fire stopping, structural information and other critical building safety elements are particularly useful.
I do think some sections could be simplified. The themes of project planning, information quality, verification and client requirements appear repeatedly throughout the document. These are important points, but reducing some of the duplication would improve readability and make the guidance more accessible, especially for smaller organisations and non-technical clients.
There is also an opportunity to include more real-world examples or short case studies. Showing what a good information handover looks like for a small refurbishment, a fire safety project, an M&E replacement scheme or a higher-risk residential building would help people understand what is expected and apply the guidance more consistently.
Finally, while the guidance promotes a proportionate approach, some smaller contractors may still see the requirements as quite demanding. Including a simple minimum-information checklist for lower-risk projects, along with more diagrams, flowcharts and summary tables, would make the document easier to navigate and help users quickly understand the key requirements.
The key aspect of the naming conventions and level of information required is that this needs to include the requirements of the organisation who will end up managing the building. Otherwise all that happens is the handover documents will sit in a folder somewhere and will be pulled out only when someone needs to do dep dive work to identify why something went wrong in the building. It’s like a publishing house producing a comprehensive book of the works of Shakespeare in German, and expecting someone in England to use it to put on a play.
Neil Yeomans
Hi Neil – I absolutely agree. That is phase two which kicks off in October with meetings to try and determine the HOW.
Many thanks for forwarding, George. Admittedly I am time poor but a few comments / observations.
Have The Higher-Risk Buildings (Keeping and Provision of Information etc.) (England) Regulations 2024 been considered? I cannot find it referenced in the draft. Whilst I accept the work deliberately zooms out beyond HRBs, for completeness I think it should be referenced (particularly Schedule 1).
On that subject, I welcome the decision to zoom out (which we touched on in the original business case discussions) . I have thought for a long time that the ‘golden thread concept’ should be applied proportionately to any scheme. The draft is right to frame the question around what information is proportionately required for the safe and successful operation of an asset, rather than around the discharge of individual regulatory obligations.
As-built information has been a point of discussion for many years and a source of frustration in practice. People have genuinely read “final construction issue” and “record drawings” as meaning as-built.
Over the last nine plus years, where property owners have had cause to carry out building safety investigations, the record has been either missing or unlocatable and when found it more often than not accurately reflected what was actually built. That is before dealing with the discipline needed to keep information current through the occupation phase and the ‘changes’ a building undergoes. Removing the ambiguity in the term is a necessary first step.
The HOW will be difficult! A significant element of the HOW is producing an output with sufficient detail for those instigating the work. But before that, the WHY has to be sold to those holding the purse strings, meaning asset owners and operators. (which is why it is so great to see many who fall into that category in the list of supporters / contributors!)
We flagged in 2024 that OPEX requirements are not cascaded down the supply chain, because the end user does not fully understand them, cannot communicate them, or is focused on immediate CAPEX.
Marc Bradfield
NCG
Is the document aimed at the entire industry? If so, I am not sure that those at the smaller end of the scale will see this as being a proportionate read to identify what they should do at the end of a project? It is very long.
Hi – yes, you are right that it is a long document but as we worked through it with over 100 firms contributing, we needed to cover the various differen aspects.As a fellow SME, what we need to know is how to comply and that will be covered in the next series of workshops covering the HOW.
If you or anyone would like an invite, email george.stevenson@BIM-in-AM.com
Please could you email me a copy to robwclarke@hotmail.com, Thank you
George/Richard,
If you could email a copy to marc.bradfield@nucleuscompliance.com, it would be appreciated.
Regards
Marc
Please email a copy to steve.peckett@vinci-construction.com Thank you.
Please email a copy to joshua.warner@gpa.gov.uk
Please email a copy to Helen.sturdy1@nhs.net
bit concerned with the wording of as builts and no clear and concise definition who provides and limitations. we as architects do not provide as-builts but final record issue information and think this needs clearer definition within the document to avoid interpretation otherwise?
agree with this point
Why are the emojis in the comments so massive? It makes it difficult to read the comments.
The ITFG As-Built Requirements draft is a well-intentioned effort to improve the consistency and quality of information delivered at project completion.
However, in its current form, it risks doing more harm than good.
The document does not establish a sufficiently clear and concise definition of what constitutes as-built information and instead blurs the boundaries between as-built records, handover / O&M information, BIM processes, asset management requirements, inspection and test plans, and broader validation activities.
This scope drift creates ambiguity for dutyholders and information authors, increasing the likelihood of inconsistent interpretation and implementation.
The draft could also lead to different organisations interpreting requirements in different ways, reducing rather than improving consistency across the industry.
Without a concise, clear definition of ‘as-built’ teams will produce large volumes of unnecessary information, clients will receive documentation that makes it harder to understand the completed building, and contractual disputes will occur over what information is actually required.
A more effective approach would be to define as-built information clearly and narrowly as a record of the completed physical building, with a SEPARATE guidance covering handover requirements, O&M information, asset management, and validation activities.
This would improve clarity, reduce duplication, and encourage more consistent adoption across the industry.
There is a lot of information handed over at the end of a project – not all of it what the industry would define as ‘as-built’. The document recognises this to some degree in the content, but retains the title -as-built’ which I think is a bit confusing as the section on ‘as-built’ is actually quite small and does not deal with the practical difficulties experienced in its definition and preparation.
agree with this
I would argue that the handover information should include reliable and accurate as-built records. If some of information cannot reasonably and practically verified, then that should be classified as “un-verified”
Whilst the intent of the document is good, it is very long and repetitive – if it is aimed at the ‘whole of the industry’ it needs to be much shorter and more succinct, to make it more accessible and the ‘go-to’ guide. There is a lot of ‘history’ and background explanation in it, which if it needs to stay could become a short statement at the start explaining the need for the guide with more detail in an appendix, leaving the body of the document for the practical information which is getting lost at present.
I agree
I need a downloadable copy to study this properly. richard@deploi.co.uk
Hi Richard – I have just emailed it. Regards – George
Looks good – I will review this in relation to compliance and handover, and alignment to government soft landings (covering both the information requirements and technical assurance). Please email me a copy to michael.bracken@gpa.gov.uk