As Built Information Group Meetings 20-10-2026

BIMINAM AS BUILT INFORMATION MEETING, 20-10-2026

Meeting 10 | 20 October 2026 | One-Page Meeting Summary

Overview

The meeting marked the start of Phase 2 of the As-Built Information initiative, moving from defining what building owners and occupiers need to understanding who should provide that information and how it should be captured, verified and delivered.

The group reaffirmed the importance of producing practical, industry-supported guidance that improves the reliability of as-built information throughout a building's life.

Key Discussion Points

  1. Consultation feedback and existing guidance

Approximately 85 detailed consultation comments have been received. Anthony Taylor will review and categorise these into comments relating to the existing guidance and matters requiring consideration in Phase 2. The current document will remain open for consultation and be refined as Phase 2 progresses, rather than being finalised immediately.

  1. Defining responsibilities – the WHO

The group discussed identifying the parties responsible for producing, checking, approving and receiving information throughout a construction project. Peter Anderson suggested starting with the WHO before tackling the more complex HOW. Existing roles, responsibilities and competencies should be considered rather than reinventing established industry guidance.

  1. Establishing the process – the HOW

Reliable as-built information must be progressively captured and verified, not reconstructed at handover. The discussion highlighted the importance of recording construction changes, maintaining configuration control and ensuring that the information delivered accurately represents what has been built.

The RIBA Plan of Work stages were proposed as a possible organising framework, with reference to existing standards including ISO 19650.

  1. Client requirements and responsibilities

Clients must establish their information requirements at the outset, supported by competent professional advice. These requirements should be reflected in procurement, contracts, delivery processes and verification arrangements. The group recognised that many clients currently lack the expertise to specify what they need.

  1. Applicability to all buildings and projects

The guidance should be applicable to all building types, including higher-risk buildings, other occupied buildings, new construction and alterations to existing assets. Requirements should be proportionate to project scale and risk, without compromising the fundamental quality of information.

  1. Improving the reliability of the Golden Thread

The group highlighted continuing discrepancies between design information, asset models and actual installations. One example involved approximately 1,400 sprinkler heads recorded digitally compared with almost 2,000 in the O&M information. Such discrepancies demonstrate why digital information management alone cannot guarantee reliable records.

Agreed Direction and Next Steps

  1. Consultation review: Anthony Taylor and a smaller group will review the consultation feedback and identify matters for Phase 2.
  2. Review scope: Revisit the original Terms of Reference to maintain a clear, focused approach.
  3. Map responsibilities: Peter Anderson will develop an initial list of key project participants and responsibilities for discussion.
  4. Develop a methodology: Establish a structured, repeatable process for capturing and verifying information, informed by existing standards and industry practice.
  5. Prepare client guidance: Consider specific advice to help clients commission and manage reliable as-built information.
  6. Future outputs: Explore a possible suite of complementary guidance documents covering WHAT information is required, HOW it is produced and WHO is responsible.
  7. Next meeting: Allow approximately two weeks for preparatory work before reconvening.

Overall Conclusion

The group broadly supported progressing Phase 2 through a structured, collaborative and consensus-led approach. The priority is to move beyond defining the required information and establish a practical, proportionate and accountable process that ensures the information handed over genuinely reflects what has been constructed.

The intended outcome is guidance that helps clients, designers, contractors and building operators work together to create dependable information that supports building safety, maintenance, compliance and effective asset management throughout the building lifecycle.